Mumbai/Project record

MahaRERA · the public record

CHETAN RACHANA

VILLAGE KOLAD TAL ROHA · Chetan Builders & Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jan 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jan 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000019528

Delivery and registration

When is the project declared for completion?

CHETAN RACHANA is registered with MahaRERA as P52000019528 and the promoter has declared completion for 30 Jan 2024.

30 Jan 2024

declared completion

32months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000019528
Registered on08 Feb 2019
Promoter-declared completion30 Jan 2024
Current statusCertificate Signed
Against todayabout 32 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for CHETAN RACHANA record 21 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 21 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Chetan Builders Developers is the promoter of record on 31 projects registered with MahaRERA, 7 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

31projects

registered with MahaRERA

7flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for CHETAN RACHANA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
CHETAN RACHANA1G+731 Jan 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at VILLAGE KOLAD TAL ROHA, PLOT NO. 02 GUT NO. 146, Thane, Thane, 402304. Per the filed land record, the plot is bounded to the north by GUT NO 145, to the south by 9 MTR WIDE ROAD, to the east by GUT NO 147 and to the west by GUT NO 145. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Village Kolad Tal Roha

Ekdanta Plaza
possession by Dec 2026 · Ekdanta Realtors
Sky Residency
possession by Dec 2028 · SKY Construction
Prerana Heights
possession by Dec 2029 · Not Available
Lush
Not filing quarterly progress reports · declared completion Jun 2026 · Smita Rajan Akshekar
SAI Shubharambh Residency
Not filing quarterly progress reports · declared completion Dec 2025 · Shreeraj Asmi Infra LLP
Kolad Hills
Not filing quarterly progress reports · declared completion Dec 2025 · Saifortune Builders AND Developers Priva

Other RERA-registered projects in Raigarh

Chinmay Plaza
possession by Dec 2026 · Atmaram Narayan Shinde
Chintamani Apartment
possession by Mar 2031 · Chintamani Ramchandra Sonawane
Chintan Apartment
possession by Dec 2027 · Vaishnavi Builders & Developers
Chitra Enclave
possession by Jun 2028 · Mudra Relaty
Chitrapatjanak Dadasaheb Phalke Township - Phase 1
declared completion Jun 2026 · Anukarati Homes Pvt Ltd
Cidade Vida
possession by Dec 2029 · Bhide Lifespaces

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026