MahaRERA Property Intelligence · Thane

Courtyard - Asteria C

P51700048420 · Majiwade · promoter Courtyard Real Estate

Certificate SignedDue 31 Dec 2027

Delivery & Registration

MahaRERA registrationP51700048420
Registered on03 Jan 2023
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today17 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Courtyard Real Estate is the promoter of record on 9 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Courtyard - Asteria C Retail1G+431 Dec 2027

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court591 of 20172017Pending

Location, Land & Connectivity

Located at Majiwade, Pokhran Road No. 2, Mumbai, Mumbai Suburban, 400610. Per the filed land record, the plot is bounded to the north by Central Green, to the south by Pokhran Road No 2, to the east by Amenity Park and to the west by Tata Serein. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park13 km
Andheri MIDC / SEEPZ14 km
Chhatrapati Shivaji Int'l Airport18 km
Bandra Kurla Complex (BKC)20 km
Lower Parel / Worli business district28 km
Nariman Point / Fort36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Courtyard Real Estate Private Limited is the promoter on 8 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Courtyard Real Estate Private Limited project & its RERA track record →

Other flagged projects by Courtyard Real Estate Private Limited

Courtyard Real Estate Private Limited
FlaggedThane
Courtyard Real Estate Private Limited
FlaggedThane
Courtyard Real Estate Private Limited
FlaggedThane
Courtyard Real Estate Private Limited
FlaggedThane
Courtyard Real Estate Private Limited
FlaggedThane
Courtyard Real Estate Private Limited
FlaggedThane

Other RERA-registered projects in Majiwade

Infinity Towers
possession by Dec 2026 · T Bhimjyani Realty Pvt.ltd.
Raunak Imperial
possession by Dec 2026 · Raunak Avenue Realty
ZEN
possession by Dec 2026 · Neelkanth Realtors PVT LTD
Serein Phase II
possession by May 2027 · Ardent Properties Private Limited
Mahavir Spring -Daffodils-P3
possession by Dec 2027 · Vinayak Developers
Courtyard - Asteria A
possession by Dec 2027 · Courtyard Real Estate Private Limited

Major developers building in Majiwade

Other RERA-registered projects in Thane

Courtyard - Florence
declared completion Dec 2021 · Courtyard Real Estate Private Limited
Courtyard - Ivy
declared completion Dec 2021 · Courtyard Real Estate Private Limited
Courtyard - Onyx
declared completion May 2023 · Courtyard Real Estate Private Limited
Courtyard - Ornella
declared completion May 2023 · Courtyard Real Estate Private Limited
Courtyard - Rozanne
declared completion May 2025 · Courtyard Real Estate Private Limited
Creative Marvel
possession by May 2028 · Creative Home

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026