Mumbai/Project record

MahaRERA · the public record

D N Nagar Krishna CHS Ltd

D N Nagar Andheri West · Sai Siddhant Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800007005

Delivery and registration

When is the project declared for completion?

D N Nagar Krishna CHS Ltd is registered with MahaRERA as P51800007005 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800007005
Registered on17 Aug 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for D N Nagar Krishna CHS Ltd record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 26 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sai Siddhant Developers is the promoter of record on 19 projects registered with MahaRERA, 10 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

19projects

registered with MahaRERA

10flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for D N Nagar Krishna CHS Ltd in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.

BuildingWingsFloorsDeclared completion
D N Nagar Krishna CHS Ltd1G+17-

Legal and disputes

What disputes are disclosed?

12 complaints are on the MahaRERA record for D N Nagar Krishna CHS Ltd, with orders passed in 12 of them.

12complaints

12with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000002392327/03/2018raghu kumar tekriwal vs JAYESH TANNAorder passed
CC00600000007847514/03/2019Surendranath Mahabala Lahari vs Sai Siddhant Developersorder passed
CC00600000007844215/03/2019Sanjiv Kochhar vs Sai Siddhant Developersorder passed
CC00600000019604216/02/2021Sanjiv Kochhar vs Sai Siddhant Developersorder passed
CC00600000021020904/03/2022Raghu Kumar Tekriwal vs M/s Sai Siddhant Developersorder passed
CC00600000025148215/06/2022Mohini Ludhani vs Sai Siddhant Developersorder passed
CC00600000025148615/06/2022Bharat Ludhani vs Sai Siddhant Developersorder passed
CC00600000025170003/07/2022Veenu Odharani vs Sai Siddhant Developersorder passed
CC00600000039695013/08/2023Salomi Chakraborty vs Shree Sai Group Of Companiesorder passed
CC00600000058085821/06/2024Jayshree Hansraj Gada vs Sai Siddhant Developersorder passed
CC1250107831/03/2025SACHIN SURESH RAUT vs Sai Siddhant Developersorder passed
CC1250201019/06/2025Gurmukh Chandiram Aidasani vs Sai Siddhant Developersorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High Court Of Judicature At Bombay6282017Hearing

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2022This is to bring on record that due to uncertainties, flip flops and non-clearance of the policies under the scheme of 33(5) of MHADA, there has been unintentional delay in the com
31 Dec 202231 Dec 2022I Mr. Jayesh Tanna,say that, due to some issues which aroused with the society as well as due to change in permission related norms where in MHADA became the planning authority, ge

Location, Land & Connectivity

Located at D N Nagar Andheri West, Ganesh Chawk, Borivali, Mumbai Suburban, 400053. Per the filed land record, the plot is bounded to the north by Mhada Boundry, to the south by Bldg No 2, to the east by 12 Sq mtr and to the west by Bldg No 4. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Chhatrapati Shivaji Int'l Airport5 km
Bandra Kurla Complex (BKC)8 km
Powai / Hiranandani business park8 km
Lower Parel / Worli business district14 km
Nariman Point / Fort22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sai Siddhant Developers is the promoter on 5 MahaRERA-registered projects, of which 5 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Sai Siddhant Developers project & its RERA track record →

Other flagged projects by Sai Siddhant Developers

Sai Siddhant Developers
Past its declared completion dateMumbai Suburban
Sai Siddhant Developers
Past its declared completion dateMumbai Suburban
Sai Siddhant Developers
Registration suspendedMumbai Suburban
Sai Siddhant Developers
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Andheri West

Royale
possession by Sep 2026 · Khoker Synergy Developers
Transcon Triumph Tower 3
possession by Sep 2026 · Transcon Triumph Phase 2 Private Limited
ARC ONE
possession by Dec 2026 · Chandra Gupta Estates Private Limited
MDM Maestro
possession by Dec 2026 · MDM Realty LLP
Platinum Grandeur
possession by Dec 2026 · Platinum Strategic Developers LLP
Vengurlekars Chaitra
possession by Dec 2026 · Vengurlekars Shreesai Builders And Devel

Major developers building in Andheri West

Other RERA-registered projects in Mumbai Suburban

D N Nagar Shivneri CHS Ltd
declared completion Mar 2023 · Sai Siddhant Developers
D N Nagar Suryakiran CHS Limited
declared completion Dec 2021 · Sai Siddhant Developers
D Solitaire
declared completion Jun 2026 · Krishnan AND Kamal Associates
Dadamiyas Deluxe Apartment
declared completion Mar 2023 · Dadamiya Infrastructure & Deluxe Inf
Dadamiyas Emerald
possession by Mar 2027 · Dadamiya Infrastructure LLP
Dahisar Garden View
possession by Mar 2029 · Vallabh Vihaan Shreeji Constructions

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026