30 Sep 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800003743

Delivery and registration

When is the project declared for completion?

DAHISAR UJWAL C.H.S. LTD is registered with MahaRERA as P51800003743 and the promoter has declared completion for 30 Sep 2020.

30 Sep 2020

declared completion

72months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800003743
Registered on06 Aug 2017
Promoter-declared completion30 Sep 2020
Current statusCertificate Signed
Against todayabout 72 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for DAHISAR UJWAL C.H.S. LTD record 13 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 13 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

The Kt Group is the promoter of record on 4 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

4projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for DAHISAR UJWAL C.H.S. LTD in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22.

BuildingWingsFloorsDeclared completion
DAHISAR UJJAWALA CHS LTD1G+22-

Legal and disputes

What disputes are disclosed?

7 complaints are on the MahaRERA record for DAHISAR UJWAL C.H.S. LTD, with orders passed in 7 of them.

7complaints

7with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000000132324/10/2017Mr Tarun Joshi vs The KT Group Ujjawala through its Partners Mr Sandeep Sheth Mr AMit Patil and Mr Dharmesh I Tannaorder passed
CC00600000000101707/10/2017Pushpa Malpani vs Dharmesh I Tannaorder passed
CC00600000001214028/11/2017RIDDHI CONSTRUCTION CO. vs THE KT GROUP UJJWALAorder passed
CC00600000002318219/02/2018Mr Sachin S. Shardul and Mr Suresh S. Shardul vs M/s The KT Group Ujjwalaorder passed
CC00600000002318919/02/2018Mrs Savita Sanjay Bidaye and Sunanda Madhu Sudan Bidaye vs M/s The KT Group Ujjwalaorder passed
CC00600000005564604/08/2018KUNHAL SHAH vs THE KT GROUP UJJWALAorder passed
CC00600000005597830/08/2018Samir Bhulani vs KT Group Ujjwala, through its partnersorder passed

Legal & Litigation

The promoter has declared 4 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
State Consumer Dispute Redressal3752017Hearing
Hogh Court Of Bombay Ordinary Original Civil Jurisdiction3272017Pre Admission
High Court Of Bambay Ordinary Original Civil Jurisdiction872017Pre Admission
Ld Judicial Magistrate Kolkata34442016Hearing

Location, Land & Connectivity

Located at DAHISAR EAST, DAHISAR, Borivali, Mumbai Suburban, 400068. Per the filed land record, the plot is bounded to the north by PROPERTY BEARING S NO 290 H NO 10, to the south by PROPERTY BEARING S NO 290 H NO 4, to the east by PROPERTY BEARING S NO 290 H NO 17 and to the west by SURVEY NO 191 HISSA NO 5. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ14 km
Powai / Hiranandani business park16 km
Chhatrapati Shivaji Int'l Airport19 km
Bandra Kurla Complex (BKC)21 km
Lower Parel / Worli business district29 km
Nariman Point / Fort37 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dahisar East

Bhaveshwar Heights
possession by Sep 2026 · Shree Krishna Real Estate And Developers
Padma Apartment CO-Operative Housing Society Limited
possession by Sep 2026 · Haritara Construction Company Private Li
Jeandveekedarnath
possession by Dec 2026 · JE AND VEE Infrastructure
Shri Upendra Chsl
possession by Dec 2026 · Harshal Enterprises
Swayam Niketan
possession by Dec 2026 · Jainam Associates
A And O Eminente
Not filing quarterly progress reports · possession by Dec 2026 · Ashapura Housing Private Limited

Major developers building in Dahisar East

Other RERA-registered projects in Mumbai Suburban

Daivi Eterneety
possession by Dec 2026 · Yash Development
Damji Shamji Avenuee
possession by Dec 2029 · OV Buildcon LLP
Damji Shamji Business 78
declared completion Jun 2025 · Fortune Construction Company
Damji Shamji Corporate Square - Wing C
possession by Dec 2026 · Coronate Constructions
Damji Shamji Zenith
possession by Dec 2027 · Chandrakant AND CO
Damyanti Villa CO Operative Housing Society
possession by Dec 2026 · Damyanti Villa CO Operative Housing Soci

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026