MahaRERA Property Intelligence · Mumbai City

DUDHWALA AQUAGEM

P51900011349 · 400008 · promoter Castle Realtors Private

Certificate SignedDue 30 Dec 2023

Delivery & Registration

MahaRERA registrationP51900011349
Registered on31 Aug 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Castle Realtors Private is the promoter of record on 16 projects, of which 3 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+37.

BuildingWingsFloorsDeclared completion
BUILDING NO 1-4th to 35th FLOORS1G+37-
BUILDING NO 2 - 4th to 18th FLOORS1G+19-
BUILDIG NO 3-REHAB UNITS1G+4-

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000037483923/03/2023Mohammed Arif vs Castle Realtors Private Limitedorder passed

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court2112014Active
Bombay High Court2132017Active

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202330 Dec 2023Due to Covid 19 the real estate market is suffering huge loss and till date could not achieve recover, due to financial instability and other major issues we could not the said pro

Location, Land & Connectivity

Located at 400008, Nesbit Road, Ward E, Mumbai City, 400010. Per the filed land record, the plot is bounded to the north by CS NO 375, to the south by NESBIT ROAD, to the east by CS NO 378 AND 2-378 and to the west by CS NO 377. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Lower Parel / Worli business district3 km
Nariman Point / Fort5 km
Bandra Kurla Complex (BKC)11 km
Chhatrapati Shivaji Int'l Airport14 km
Powai / Hiranandani business park18 km
Andheri MIDC / SEEPZ18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mazgaon

Harbour Heights
Not filing quarterly progress reports · possession by Dec 2026 · Shree Naman Estate Projects Private Limi
A. M. Residency
possession by Dec 2026 · Alfa Mana Realtors PVT LTD
Hamilton Mansion
possession by Dec 2026 · M.i.realty Private Limited
Shreepati Coronet
possession by Dec 2026 · Shreepati Build Infra Investment Limited
Deja View
possession by Mar 2027 · Zahida ABU Asim Azmi
Splendour
possession by Mar 2027 · Netra Developers

Major developers building in Mazgaon

Other RERA-registered projects in Mumbai City

Dudhwala Aquapearl
declared completion Dec 2022 · Dudhwala Real Estate AND Investment
Dudhwala Complex-Phase 2
declared completion Jun 2022 · Rock Corner Developer Private Limited
Duldul Heights
possession by Dec 2030 · Saafi Infra LLP
Durvankur
declared completion Dec 2021 · Sameer Mukund Natu
Dvayam
possession by Dec 2029 · Kabra Estate AND Investment Consultants
Earth 280
possession by Aug 2027 · Earth Builders

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026