Mumbai/Project record

MahaRERA · the public record

EKDANT ENCLAVE

. · SAEE CONSTRUCTIONS AND BUILDERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

60units filed as unsoldInventory · 16 September 2026
31 Dec 2032declared completionMahaRERA registration · read 02 Jul 2026
84registered unitsMahaRERA registration · read 02 Jul 2026

The record · free to read

Registration read 02 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2032

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 02 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PR1270002502655

Delivery and registration

When is the project declared for completion?

EKDANT ENCLAVE is registered with MahaRERA as PR1270002502655 and the promoter has declared completion for 31 Dec 2032.

31 Dec 2032

declared completion

75months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 02 Jul 2026

MahaRERA registrationPR1270002502655
Registered on09 Mar 2026
Promoter-declared completion31 Dec 2032
Current statusCertificate Signed
Against today75 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for EKDANT ENCLAVE record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 02 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Saee Constructions is the promoter of record on 5 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

5projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 02 Jul 2026

Sales

How much has actually been sold?

In EKDANT ENCLAVE, 0 of 64 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 64 remain available.

0%sold

0 of 64 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. The project registers 84 homes in total, while this sold/unsold inventory filing covers 64 of them.

Source · MahaRERA sold/unsold inventory filing · read 02 Jul 2026

The inventory filing also declares: 20 not for sale.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for EKDANT ENCLAVE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 16 September 2026

What the filings record, home by home

Read from MahaRERA on 16 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 4 homes carry one, and 60 of the 84 are recorded unsold. Since we started watching this ledger, 4 homes have moved out of the unsold list, most recently on 07 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
FLAT NO. 101512 sqftRs 20.00 lakh to Rs 29.50 lakh2 filed on this stack, floors 4–5

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6 and 84 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
EKDANT ENCLAVE A WING1G+642-
EKDANT ENCLAVE B WING1G+642-

Unit mix on the filing: 84 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at ., MADHALE AAVAD, Mahad, Raigarh, 402302. Per the filed land record, the plot is bounded to the north by SURVEY NO. 8/2, to the south by SURVEY NO. 152, to the east by GP ROAD and to the west by SURVEY NO. 8/1. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~123 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort117 km
Lower Parel / Worli business district123 km
Bandra Kurla Complex (BKC)127 km
Chhatrapati Shivaji Int'l Airport129 km
Powai / Hiranandani business park130 km
Andheri MIDC / SEEPZ133 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other flagged projects by Not Available

Not Available
FlaggedMumbai Suburban

Other RERA-registered projects in Birwadi

Hari OM Residency
possession by Dec 2026 · Aparna A Bhosale
Shelter Plaza
possession by Dec 2026 · Mahira Developers
SAI Prasad
possession by Dec 2027 · Dilip Waman Gadgil
Shiv Shalini Complex
possession by Dec 2028 · Ganarai Developers
Shreeji Corner
declared completion Jun 2024 · Shreeji Enterprise
Laxmi Heights
Past its declared completion date · declared completion Dec 2023 · Shadulla Hussain Savratkar

Other RERA-registered projects in Raigarh

Ekdant Residency
declared completion Mar 2026 · Kiran Madhav Nangare
Ekdanta Plaza
possession by Dec 2026 · Ekdanta Realtors
Ekveera Sanidhya Apartment
declared completion Oct 2024 · Satish Appasaheb Daule
Elanza - Bungalow
declared completion Dec 2024 · Satish Vallabhdas Sutaria
Elcarim Enclave
possession by Dec 2026 · Elcarim Developers AND Properties Privat
Elegant Phase - I
possession by Dec 2026 · Dgains Bhoomi Nirmaan Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026