30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000023160

Delivery and registration

When is the project declared for completion?

LAXMI HEIGHTS is registered with MahaRERA as P52000023160 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000023160
Registered on04 Dec 2019
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for LAXMI HEIGHTS record 17 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 17 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for LAXMI HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
LAXMI HEIGHTS A WING1G+431 Dec 2022
LAXMI HEIGHTS B WING1G+331 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at MOHALLA, KHATIK ALI, Mahad, Raigarh, 402302. Per the filed land record, the plot is bounded to the north by SURVEY NUMBER 35, to the south by 38-1D 158 52, to the east by GRAM PANCHAYAT ROAD and to the west by SURVEY NUMBER 38-1A. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Birwadi

Hari OM Residency
possession by Dec 2026 · Aparna A Bhosale
Shelter Plaza
possession by Dec 2026 · Mahira Developers
SAI Prasad
possession by Dec 2027 · Dilip Waman Gadgil
Shiv Shalini Complex
possession by Dec 2028 · Ganarai Developers
Ekdant Enclave
possession by Dec 2032 · Not Available
Shreeji Corner
declared completion Jun 2024 · Shreeji Enterprise

Other RERA-registered projects in Raigarh

Laxmi Heights
possession by Sep 2026 · Shreesunder Developers
Laxmi Icon
declared completion Jun 2024 · Laxmi Realty
Laxmi Icon
possession by Mar 2030 · Laxmi Associates
Laxmi Krupa
declared completion Jun 2023 · Mahadev Jagannath Shinde
Laxmi Niwas
possession by Dec 2026 · Santosh Dhanaji Mhatre
Laxmi Pooja
declared completion Sep 2024 · Shraddha Enterprises

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.