MahaRERA Property Intelligence · Thane

Evergreen Heights

P51700000095 · promoter Vijay Vasudev Wadhwa

Certificate SignedDue 31 Dec 2018

Delivery & Registration

MahaRERA registrationP51700000095
Registered on30 Jun 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 91 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Vijay Vasudev Wadhwa is the promoter of record on 27 projects, of which 3 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+34.

BuildingWingsFloorsDeclared completion
Evergreen Heights1G+3431 Dec 2018

Complaints & Orders

3 complaints are on the MahaRERA record for this project, with orders passed in 3. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000004450014/05/2018Arif Ansari vs NAVIN MAKHIJAorder passed
CC00600000005571709/08/2018Mr Ankush K Malhotra vs Mr Vijay V Wadhwaorder passed
CC00600000019666211/06/2021NINAD RANE vs WADHWA CONSTRUCTIONSorder passed

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400605. Per the filed land record, the plot is bounded to the north by Plot bearing CTS No 102, to the south by Central Railway Line, to the east by Plot bearing CTS No 102 and to the west by Plot bearing CTS No 186 and Nalla. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~15 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park15 km
Andheri MIDC / SEEPZ17 km
Chhatrapati Shivaji Int'l Airport20 km
Bandra Kurla Complex (BKC)22 km
Lower Parel / Worli business district30 km
Nariman Point / Fort37 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kalwa

Maple Enclave
possession by Sep 2026 · Mandar Construction AND Developers
Shivanand SRA CHS
possession by Dec 2026 · Madhur Manohar RAO
Ashar Arize Galleria
possession by Jan 2027 · Ms Ashar Ventures
Ashar Arize N.m.m. Society Tower A
possession by Jan 2027 · Ms Ashar Ventures
Nandanvan Homes-Building B
possession by Mar 2027 · Shree Krupa Builders
Radha Krishna Park
possession by Jun 2027 · Space Developers

Major developers building in Kalwa

Other RERA-registered projects in Thane

Evergreen Residency C Wing
declared completion Dec 2022 · Balaji Construction
Evergreen Residency Wing A,b,d,e
declared completion Dec 2022 · Balaji Construction
Ewar Complex
declared completion Dec 2020 · Ewar Constructions Private Limited
Expert Home Construction LLP
declared completion Dec 2022 · Expert Home Construction LLP
Expert Home Construction LLP
declared completion Dec 2024 · Expert Home Construction LLP
F Neelkanth Greens
possession by Mar 2028 · Neelkanth Mansions And Infrastructure Pv

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026