Mumbai/Project record

MahaRERA · the public record

FINESSIA 4TH FLOOR TO 9TH FLOOR

BANDRA (WEST) · SHANTI CONSTRUCTION

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800017112

Delivery and registration

When is the project declared for completion?

FINESSIA 4TH FLOOR TO 9TH FLOOR is registered with MahaRERA as P51800017112 and the promoter has declared completion for 30 Sep 2019.

30 Sep 2019

declared completion

84months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800017112
Registered on13 Jul 2018
Promoter-declared completion30 Sep 2019
Current statusCertificate Signed
Against todayabout 84 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for FINESSIA 4TH FLOOR TO 9TH FLOOR record 5 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 5 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Shanti Construction is the promoter of record on 113 projects registered with MahaRERA, 18 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

113projects

registered with MahaRERA

18flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for FINESSIA 4TH FLOOR TO 9TH FLOOR in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
FINESSIA 4TH FLOOR TO 9TH FLLOR1G+630 Sep 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at BANDRA (WEST), 27TH ROAD, Mumbai, Mumbai Suburban, 400050. Per the filed land record, the plot is bounded to the north by PLOT NO 218, to the south by PLOT NO 220, to the east by 27TH ROAD and to the west by PLOT NO 207. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shanti Construction is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Bandra West

Bandra Boon CHS LTD
possession by Sep 2026 · Mass Jaks Associate Ventures
Aryan Tower
Not filing quarterly progress reports · possession by Dec 2026 · Suchit Developers
Brightland
possession by Dec 2026 · Sambhavparshva Developers Private Limite
Hill Casa
possession by Dec 2026 · Husain Taher Patni
Hill View
possession by Dec 2026 · L Nagpal Builders LLP
Manthan Embassy
possession by Dec 2026 · Manthan Development Corporation

Major developers building in Bandra West

Other RERA-registered projects in Mumbai Suburban

Flora
possession by Mar 2032 · UVK Divine Realty
Flora Headquarters
possession by Dec 2029 · Victory Realtors Private Limited
Florence Heights A And B Wing
declared completion Jun 2026 · M/s Vinayak Developers
Forefront Northeast-100
possession by Dec 2028 · Forefront Realty Private Limited
Forefront Primeria
declared completion Dec 2025 · Forefront Private Limited
Forest Hills Ph 1 At The Prestige City
possession by Dec 2030 · Prestige Mulund Realty Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026