30 Nov 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Nov 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700032684

Delivery and registration

When is the project declared for completion?

Fiora A, B and C is registered with MahaRERA as P51700032684 and the promoter has declared completion for 30 Nov 2025.

30 Nov 2025

declared completion

10months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700032684
Registered on24 Jan 2022
Promoter-declared completion30 Nov 2025
Current statusCertificate Signed
Against todayabout 10 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Fiora A, B and C record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Fiora A, B and C in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+24.

BuildingWingsFloorsDeclared completion
Fiora A1G+2430 Nov 2025
Fiora B1G+2430 Nov 2025
Fiora C1G+2430 Nov 2025

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Fiora A, B and C, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000047992903/04/2024Kiran Murlidhar Jakkulwar vs Ladha codename premierorder passed

Location, Land & Connectivity

Located at Dombivali, Hedutane, Mumbai City, Mumbai City, 421203. Per the filed land record, the plot is bounded to the north by 24 by 1B and 260 by 1, to the south by 260 by 3, to the east by 212 by 2 and 3 and 260 by 4 and to the west by 260 by 2. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Lodha Developers Limited is the promoter on 171 MahaRERA-registered projects, of which 9 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Lodha Developers Limited project & its RERA track record →

Other flagged projects by Lodha Developers Limited

Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedThane

Other RERA-registered projects in Hedutane

Ambrin 3
possession by Sep 2026 · Impressions
Liana C
possession by Sep 2026 · Lodha Developers Limited
Casa Belvedere
possession by Oct 2026 · Lodha Developers Limited
Fiora G And H
possession by Oct 2026 · Lodha Developers Limited
Patels Pearl
possession by Oct 2026 · Pramukh Developers
Ashokas Empire
possession by Dec 2026 · Ashokas Empire

Major developers building in Hedutane

Other RERA-registered projects in Thane

Fiora D
declared completion Jan 2026 · Lodha Developers Limited
Fiora E
declared completion Mar 2026 · Lodha Developers Limited
Fiora F
declared completion Aug 2026 · Lodha Developers Limited
Fiora G And H
possession by Oct 2026 · Lodha Developers Limited
Fiora I
possession by Feb 2030 · Lodha Developers Limited
Fiora J
possession by Jan 2029 · Lodha Developers Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.