Mumbai/Project record

MahaRERA · the public record

FORTUNE GARDENS

Mumbai City · SEVEN TIDES DEVELOPERS LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900010065

Delivery and registration

When is the project declared for completion?

FORTUNE GARDENS is registered with MahaRERA as P51900010065 and the promoter has declared completion for 30 Jun 2023.

30 Jun 2023

declared completion

39months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900010065
Registered on23 Aug 2017
Promoter-declared completion30 Jun 2023
Current statusCertificate Signed
Against todayabout 39 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for FORTUNE GARDENS record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 24 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Seven Tides Developers is the promoter of record on 34 projects registered with MahaRERA, 5 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

34projects

registered with MahaRERA

5flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for FORTUNE GARDENS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+27.

BuildingWingsFloorsDeclared completion
FORTUNE GARDENS1G+27-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2023We state that the registration validity of the said project is has expired on June 30, 2022. We further state that due to certain mitigating circumstances, the balance project deve

Location, Land & Connectivity

Located at Ward ABCD, Mumbai City, 400010. Per the filed land record, the plot is bounded to the north by Formerly of NoshaferinBegum, to the south by By Victoria Road, to the east by By Victoria First Road and to the west by By Victoria Garden. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Lower Parel / Worli business district4 km
Nariman Point / Fort5 km
Bandra Kurla Complex (BKC)11 km
Chhatrapati Shivaji Int'l Airport13 km
Powai / Hiranandani business park18 km
Andheri MIDC / SEEPZ18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mazgaon

Harbour Heights
Not filing quarterly progress reports · possession by Dec 2026 · Shree Naman Estate Projects Private Limi
A. M. Residency
possession by Dec 2026 · Alfa Mana Realtors PVT LTD
Shreepati Coronet
possession by Dec 2026 · Shreepati Build Infra Investment Limited
Deja View
possession by Mar 2027 · Zahida ABU Asim Azmi
Piramal Aranya - Wing C
possession by Aug 2027 · Glider Buildcon Realtors Private Limited
Azara Residences
possession by Dec 2027 · Azara Redstone LLP

Major developers building in Mazgaon

Other RERA-registered projects in Mumbai City

Fortune Makhdoom
possession by Dec 2027 · Namla Developers Private Limited
Fortune Pearl
declared completion Jun 2025 · Nina Realtors PVT LTD
Fortune Vue A & B Wing
possession by Jan 2027 · ALF Developers
Four Seasons Private Residences Phase - 2
declared completion Dec 2025 · Provenance Land Private Limited
Fuego
possession by Jun 2027 · Hilton Infrastructure
Gadkari Paradise
possession by Dec 2030 · Gadkari Builders & Associates

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026