Galaxy Heights, Tower-IV

Malvani, Malad (West) · Mahrashtra Police Co-Operative Housing Federation Ltd.

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2030declared completionMahaRERA registration · read 02 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 02 Jul 2026

The record · free to read

Registration read 02 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2030

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 02 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PR1180002600742

Delivery and registration

When is the project declared for completion?

Galaxy Heights, Tower-IV is registered with MahaRERA as PR1180002600742 and the promoter has declared completion for 31 Dec 2030.

31 Dec 2030

declared completion

51months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 02 Jul 2026

MahaRERA registrationPR1180002600742
Registered on11 Jun 2026
Promoter-declared completion31 Dec 2030
Current statusCertificate Signed
Against today51 months to the declared date

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Galaxy Heights, Tower-IV in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 02 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+39.

BuildingWingsFloorsDeclared completion
Tower-IV of Wing A and B2G+39-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Malvani, Malad (West), Abdul Hamid Road, Gate No. 8, Borivali, Mumbai Suburban, 400095. Per the filed land record, the plot is bounded to the north by Mumbai Board Colony S No 263 part, to the south by World Bank project Scheme S No 263 part, to the east by BEST depot and marshy land and to the west by All India Radio Receiving Station. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mumbai Suburban

Galaxy Municipal Teachers CO-Operative Housing Society Limited
possession by Jun 2028 · Ajju Real Estate AND Consultants
Gami And Jaydeep Elanza
declared completion Jun 2026 · M/S Real Infrastructure CO
Gami AND Jaydeep Elora
possession by Sep 2029 · M/S Real Infrastructure CO
Gami AND Jaydeep Estella
possession by Mar 2027 · M/S Real Infrastructure CO
Gami And Jaydeep Ventura Commercial Hub
possession by Oct 2026 · M/S Real Infrastructure CO
Gami Pravah
possession by Dec 2029 · LAL Gebi Infra Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026