30 Sep 2029declared completionMahaRERA registration · read 02 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 02 Jul 2026

The record · free to read

Registration read 02 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2029

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 02 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PR1180002600003

Delivery and registration

When is the project declared for completion?

GAMI AND JAYDEEP ELORA is registered with MahaRERA as PR1180002600003 and the promoter has declared completion for 30 Sep 2029.

30 Sep 2029

declared completion

36months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 02 Jul 2026

MahaRERA registrationPR1180002600003
Registered on01 Apr 2026
Promoter-declared completion30 Sep 2029
Current statusCertificate Signed
Against today36 months to the declared date

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GAMI AND JAYDEEP ELORA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 02 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2.

BuildingWingsFloorsDeclared completion
GAMI AND JAYDEEP ELORA3G+2-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at CHEMBUR, Sainath Temple Road, Thane, Thane, 400089. Per the filed land record, the plot is bounded to the north by By open space of the MHADA & Bldg. No. 61., to the south by NDR plot 11 HPCL Bldg., to the east by By Bldg. No. 58 and to the west by By open space of the MHADA & 50.00 (15.24 sq. mtrs) Wide Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)3 km
Chhatrapati Shivaji Int'l Airport4 km
Powai / Hiranandani business park6 km
Andheri MIDC / SEEPZ7 km
Lower Parel / Worli business district10 km
Nariman Point / Fort18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

M/S Real Infrastructure CO is the promoter on 5 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by M/S Real Infrastructure CO

M/S Real Infrastructure CO
FlaggedMumbai Suburban
M/S Real Infrastructure CO
FlaggedMumbai Suburban
M/S Real Infrastructure CO
FlaggedMumbai Suburban
M/S Real Infrastructure CO
FlaggedMumbai Suburban

Other RERA-registered projects in Chembur

Orient Regency Building No. 1
possession by Dec 2026 · Orient Combine
Sree Sudarshan Heights
possession by Dec 2026 · AUM SAI Constructions Private Limited
Srushtiraj Tower
possession by Dec 2026 · Chinnaiah Venkatesh Gowda
Promesa Midtown
possession by Dec 2026 · Darshan Properties
Vishwasangam
possession by Dec 2026 · Vishwashakti Cooperative Housing Society
Ampple-ONE
possession by Mar 2027 · Amppletech Projects Private Limited

Other RERA-registered projects in Mumbai Suburban

Gami AND Jaydeep Estella
possession by Mar 2027 · M/S Real Infrastructure CO
Gami And Jaydeep Ventura Commercial Hub
possession by Oct 2026 · M/S Real Infrastructure CO
Gami Pravah
possession by Dec 2029 · LAL Gebi Infra Private Limited
Gami Pristine
possession by Dec 2028 · Siddharaj Developers Private Limited
Ganapati Baug Chsl
possession by Jan 2028 · Nitai Gaur Enterprises
Ganesh Bhuvan CHS Ltd
possession by Dec 2027 · Shree Swami Samarth Developers (project

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026