Mumbai/Project record

MahaRERA · the public record

GAURI NANDAN HEIGHTS

VADA · NEHA NATION

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000034186

Delivery and registration

When is the project declared for completion?

GAURI NANDAN HEIGHTS is registered with MahaRERA as P99000034186 and the promoter has declared completion for 31 Dec 2024.

31 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000034186
Registered on25 Mar 2022
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GAURI NANDAN HEIGHTS record 12 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 12 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Neha Nation is the promoter of record on 31 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

31projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GAURI NANDAN HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
BUILDING TYPE 11G+431 Dec 2024
BUIDLNG TYPE 21G+331 Dec 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at VADA, VADA, Vada, Palghar, 421303. Per the filed land record, the plot is bounded to the north by 0, to the south by 0, to the east by 0 and to the west by 0. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vada

Rajeshree Plaza
possession by Nov 2026 · Liva Infra Builders And Developers
Balkrushna Sankul
Not filing quarterly progress reports · possession by Dec 2026 · Sai Construction
Navkar Hills Garden View Part-1
possession by Dec 2026 · Pyramid Properties
Navkar Hills River Bay View-Part-1
possession by Dec 2026 · Navkar Holiday Homes & Water Park LL
Navkar Hills Sunrise View-Part-1
possession by Dec 2026 · Navkar Holiday Homes & Water Park LL
Navkar Hills Sunset View Part-1
possession by Dec 2026 · Navkar Holiday Homes & Water Park LL

Other RERA-registered projects in Palghar

Gayatri Park Phase 1
possession by Dec 2026 · Shree Ashtvinayak Builders & Develop
Gemini CO-OP Housing Society LTD Phase 2
possession by May 2027 · Shivani Enterprises
Gemini CO-Operative Housing Society LTD
declared completion Dec 2022 · Shivani Enterprises
Genisia Pinnacle
possession by Jun 2029 · Genisia Realty
Gharkul
declared completion Aug 2026 · Achole Infra LLP
Ghodela 27 Park View
possession by Dec 2026 · Ghodela Properties

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026