GAURI SANKALP

BADLAPUR WEST · PATIL SONS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700018384

Delivery and registration

When is the project declared for completion?

GAURI SANKALP is registered with MahaRERA as P51700018384 and the promoter has declared completion for 30 Jun 2022.

30 Jun 2022

declared completion

51months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700018384
Registered on29 Oct 2018
Promoter-declared completion30 Jun 2022
Current statusCertificate Signed
Against todayabout 51 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GAURI SANKALP record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GAURI SANKALP in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
A WING1G+531 Dec 2020
B WING1G+531 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2022Due to Pandemic Covid 19 situation there is no booking in the project.

Location, Land & Connectivity

Located at BADLAPUR WEST, MANJARLI, Ambarnath, Thane, 421503. Per the filed land record, the plot is bounded to the north by ADJOINING 9 MTR WIDE LAYOUT ROAD, to the south by ADJOINING GUT NO 12 LAND, to the east by ADJOINING GUT NO 12 PLOT NO 5 LAND and to the west by ADJOINING 6 MTR WIDE ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Badlapur

Jagannath Paradise
possession by Sep 2026 · Mayur Group
JAY Meghdoot Chsl
possession by Sep 2026 · S R Developers
Kendale Emeralds
possession by Sep 2026 · Kendale Developers
Krishna Sudama Residency
possession by Sep 2026 · SAI Homes
MAA Bhawani Empire
Deregistered by MahaRERA · possession by Sep 2026 · MAA Bhawani Construction
Raghu Anand Villa
possession by Sep 2026 · United Developers

Other RERA-registered projects in Thane

Gautam Co-Operative Housing Society
declared completion Jul 2018 · Mahesh Shriram Borkar
Gautam Enterprises
declared completion Dec 2024 · Gautam Shankarlalji Mali
Gautam Estates
declared completion Dec 2023 · Gautam Estates
Gautam Vihar Co-Operative Housing Society Ltd
possession by May 2028 · Ojass Govind Infra LLP
Gayatri Anand
possession by Dec 2028 · Gayatri Builders
Gayatri CHS LTD
declared completion Mar 2026 · Shree Angarak Enterprises Builders And D

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026