MahaRERA Property Intelligence · Palghar

Green Park- Tulip

P99000013781 · promoter Relstruct Buildcon Limited

Certificate SignedDue 31 Dec 2024

Delivery & Registration

MahaRERA registrationP99000013781
Registered on25 Oct 2017
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Relstruct Buildcon Limited is the promoter of record on 3 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
BUILDING NO 11G+531 Mar 2019
Building No 21G+531 Mar 2019
BUILDING NO 31G+531 Mar 2019
BUILDING NO 41G+531 Mar 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 201931 Dec 2020Construction vendors and material delivery issue.a) Labour/Contractors shortage b) Shortage of supply of sand & cement. c) Delay in issuance of Permissions by the authority
30 Jun 201931 Dec 2024Due to Covid-19 Pandemic there was shortage of workers and Finanical Constrains, Labour and Contractor shortage, Shortage of supply of sand and cement, delay in issuance of permiss

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 401502. Per the filed land record, the plot is bounded to the north by PLOT NO 2 ADMEASURING 4938, to the south by PLOT NO 5 ADMEASURING 10585, to the east by 15 METER WIDE INTERNAL ROAD and to the west by ADJOINING SURVEY NO 20. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~81 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ81 km
Powai / Hiranandani business park83 km
Chhatrapati Shivaji Int'l Airport85 km
Bandra Kurla Complex (BKC)88 km
Lower Parel / Worli business district95 km
Nariman Point / Fort103 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Relstruct Buildcon Limited is the promoter on 3 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Relstruct Buildcon Limited

Relstruct Buildcon Limited
Past its declared completion datePalghar
Relstruct Buildcon Limited
Past its declared completion datePalghar

Other RERA-registered projects in Kurgaon

Aakash Complex
possession by Nov 2026 · Lxmi Infra
Nisarg -Building No.2
possession by Dec 2026 · Agora Life Space
Solitaire Height
possession by Dec 2026 · Affak Arif Motiwala
Whitehill Residential
possession by Dec 2026 · Riva Realtors
Bhakti Avenue
possession by Mar 2027 · Bhakti Green Realty LLP
Aster Hans Heritage
possession by Sep 2028 · Hans Realtors

Other RERA-registered projects in Palghar

Green Valley Phase 1
declared completion Dec 2022 · Dharti Infra
Green Valley Phase 2
possession by Dec 2028 · Dharti Infra
Green View Apartment
possession by Dec 2026 · Delight Developers
Greenpark-Orchid
declared completion Oct 2023 · Relstruct Buildcon Limited
Greenpark-Rose
declared completion Dec 2020 · Relstruct Buildcon Limited
Greenway
declared completion Dec 2019 · Greenway Properties

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026