MahaRERA Property Intelligence · Mumbai Suburban

GURU-GANESH CHS LTD

P51800008377 · promoter Shree Aryadurga Developers

Certificate SignedDue 30 Oct 2021

Delivery & Registration

MahaRERA registrationP51800008377
Registered on18 Aug 2017
Promoter-declared completion30 Oct 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shree Aryadurga Developers is the promoter of record on 3 projects, of which 3 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
GURU-GANESH CHS LTD1G+8-

Complaints & Orders

3 complaints are on the MahaRERA record for this project, with orders passed in 3. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000002393129/03/2018SMT VASUDHA ARUN PARANIK vs M/S SHREE ARYADURGA DEVELOPERS PVT LTDorder passed
CC00600000019630619/03/2021Shri Narayan G Golatkar vs Shree Aryadurga Developers Pvt Ltd (Shri Rajendra Murlidhar Padhye)order passed
CC00600000047997607/04/2024Sachin A Dekhane vs Rajendra Padhyeorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Oct 202130 Oct 2020Building construction is yet to be completed due to delay in approvals. Hence, requesting for an extension.

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400081. Per the filed land record, the plot is bounded to the north by CTS NO 879, to the south by SANT DNYANESHWAR MARG, to the east by CTS NO 846-847-848 and to the west by CTS NO 878-A. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park8 km
Andheri MIDC / SEEPZ11 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)15 km
Lower Parel / Worli business district23 km
Nariman Point / Fort31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shree Aryadurga Developers Pvt. Ltd. is the promoter on 3 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Shree Aryadurga Developers Pvt. Ltd.

Shree Aryadurga Developers Pvt. Ltd.
Past its declared completion dateMumbai Suburban
Shree Aryadurga Developers Pvt. Ltd.
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Mulund East

Abundance
possession by Sep 2026 · Goodwill Developers
Jagdale Giriraj
possession by Sep 2026 · Jagdale Infrastructure Pvt. Ltd.
Richmond Ananya
possession by Sep 2026 · Divine Enterprises
Mithagar Road Ekta Chsl
possession by Dec 2026 · Palan Realty Private Limited
Bimal Apartment Chsl
possession by Dec 2026 · Rite Builders & Developers
Govind Prakash SRA CHS LTD
possession by Dec 2026 · Omsai Developers

Major developers building in Mulund East

Other RERA-registered projects in Mumbai Suburban

Guru Omkar Chsl
declared completion Jun 2023 · Siscorn Developers & Builders
Gurudarshan
possession by Mar 2028 · Balaji Builders AND Developers
Gurukripa
possession by Sep 2026 · Inspira Realty And Infra Private Limited
Gurukripa CHS
declared completion Dec 2024 · Adityaraj Enterprises
Gurukrupa CHS
declared completion Jun 2022 · Metaface India PVT LTD
Gurukrupa Dhyanam
possession by Mar 2027 · Gurukrupa Realcon Infrabuild LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026