MahaRERA Property Intelligence · Mumbai Suburban

Aveza Phase 1

P51900007527 · Mulund East, Opp Navghar Police Station, MHADA Colony, Mulund East, · promoter Tata Housing

Certificate SignedDue 29 Dec 2024

Delivery & Registration

MahaRERA registrationP51900007527
Registered on17 Aug 2017
Promoter-declared completion29 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Tata Housing is the promoter of record on 5 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~27.9% of the estimated project cost incurred as of the last certificate (₹122.68 Cr spent against a ₹439.29 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows. The declared completion date has already passed while the cost-incurred filing sits at ~27.9% — a wide gap between the promise and the money actually spent on site.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+48.

BuildingWingsFloorsDeclared completion
Tower A1G+4831 Dec 2022
Tower B1G+4031 Dec 2022
Tower C1G+4731 Dec 2022

Complaints & Orders

3 complaints are on the MahaRERA record for this project, with orders passed in 3. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000005724713/12/2018Ratul Lahiri vs TATA Housing Development Company Limitedorder passed
CC00600000005730814/12/2018Shikha Singh vs TATA Housing Development Company Limitedorder passed
CC00600000025136105/06/2022Uddhavsingh Rajput vs Tata Housing Development Company Ltd.order passed

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court20512015Ad Interim Granted By High Court On Third April Two Thousand Seventeen Not To Take Any Co Coerciv
Industrial Labour CourtThane Compliant ULP No 235 of 20162016Kept For Appearance Of The Parties And Next Date Is Twenty Six April Two Thousand Eighteen

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
29 Dec 202429 Dec 2024In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B.

Location, Land & Connectivity

Located at Mulund East, Opp Navghar Police Station, MHADA Colony, Mulund East, , Navghar Road, , Mumbai City, Mumbai City, 400081. Per the filed land record, the plot is bounded to the north by NALLA, to the south by DP ROAD, to the east by NALLA and to the west by CLUB HOUSE AND PODIUM. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park9 km
Andheri MIDC / SEEPZ11 km
Chhatrapati Shivaji Int'l Airport14 km
Bandra Kurla Complex (BKC)16 km
Lower Parel / Worli business district24 km
Nariman Point / Fort31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Tata Housing Development Company Limited is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Tata Housing Development Company Limited project & its RERA track record →

Other flagged projects by Tata Housing Development Company Limited

Tata Housing Development Company Limited
Deregistered by MahaRERAMumbai Suburban

Other RERA-registered projects in Mulund East

Abundance
possession by Sep 2026 · Goodwill Developers
Jagdale Giriraj
possession by Sep 2026 · Jagdale Infrastructure Pvt. Ltd.
Richmond Ananya
possession by Sep 2026 · Divine Enterprises
Mithagar Road Ekta Chsl
possession by Dec 2026 · Palan Realty Private Limited
Bimal Apartment Chsl
possession by Dec 2026 · Rite Builders & Developers
Govind Prakash SRA CHS LTD
possession by Dec 2026 · Omsai Developers

Major developers building in Mulund East

Other RERA-registered projects in Mumbai Suburban

Aveza Phase 2
declared completion Dec 2025 · Tata Housing Development Company Limited
Aviara
possession by Dec 2031 · Baluwala Builders
Avighna
declared completion Dec 2023 · Gangar Infrastructure
Avighna CHS LTD
declared completion Oct 2024 · Majestic Royale Developers
Avighna Residency
declared completion Dec 2018 · Konark Shakti Group Of Companies
Avira Jewellery HUB
possession by Sep 2027 · Avira Realty Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026