Mumbai/Project record

MahaRERA · the public record

Gagan Vihar Co-operative Housing Society Limited

Mulund East · Mishal Construction Private Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900006748

Delivery and registration

When is the project declared for completion?

Gagan Vihar Co-operative Housing Society Limited is registered with MahaRERA as P51900006748 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900006748
Registered on16 Aug 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Gagan Vihar Co-operative Housing Society Limited record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Mishal Construction is the promoter of record on 16 projects registered with MahaRERA, 8 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

16projects

registered with MahaRERA

8flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Gagan Vihar Co-operative Housing Society Limited in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
Gagan Vihar Co-operative Housing Society Limited1G+1331 Dec 2019

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Gagan Vihar Co-operative Housing Society Limited, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019745401/07/2021Mr. Deepak Kanhaiyalal Shimpi vs Mishal Construction Pvt. Ltdorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2020Due to Implementation of DCR-2034 and modification in some of the provision the said DCR the final approvals was got delayed. As the same was beyond our control due to reason menti

Location, Land & Connectivity

Located at Mulund East, 126/7 Navghar Lane 1, Mumbai City, Mumbai City, 400081. Per the filed land record, the plot is bounded to the north by CTS no 790A, to the south by CTS no 1138A and 1140, to the east by Municipal Road - Navghar Village Lane No 1 and to the west by CTS no 1139. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park8 km
Andheri MIDC / SEEPZ11 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)15 km
Lower Parel / Worli business district23 km
Nariman Point / Fort31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Mishal Construction Private Limited is the promoter on 12 MahaRERA-registered projects, of which 8 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Mishal Construction Private Limited project & its RERA track record →

Other flagged projects by Mishal Construction Private Limited

Mishal Construction Private Limited
Past its declared completion dateMumbai Suburban
Mishal Construction Private Limited
Not filing quarterly progress reportsMumbai Suburban
Mishal Construction Private Limited
Past its declared completion dateMumbai Suburban
Mishal Construction Private Limited
Past its declared completion dateMumbai Suburban
Mishal Construction Private Limited
Past its declared completion dateMumbai Suburban
Mishal Construction Private Limited
FlaggedMumbai Suburban

Other RERA-registered projects in Mulund East

Jagdale Giriraj
possession by Sep 2026 · Jagdale Infrastructure Pvt. Ltd.
Richmond Ananya
possession by Sep 2026 · Divine Enterprises
Mithagar Road Ekta Chsl
possession by Dec 2026 · Palan Realty Private Limited
Bimal Apartment Chsl
possession by Dec 2026 · Rite Builders & Developers
Govind Prakash SRA CHS LTD
possession by Dec 2026 · Omsai Developers
Jvms Monica Gardens
possession by Dec 2026 · JVM Spaces

Major developers building in Mulund East

Other RERA-registered projects in Mumbai Suburban

Gagangiri Complex
declared completion Dec 2021 · OM Gagangiri Development Corporation
Gagansagar
possession by Dec 2026 · HUM Developers Private Limited
Gajanan Plaza
possession by Dec 2027 · Balaji Construction Co.
Gala Ares
possession by Dec 2029 · Square ONE Realty
Gala Avenue
possession by Dec 2027 · Morarji Gala & Sons
Gala Hub
declared completion Aug 2025 · Gala Comp

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026