Nehru Nagar Madhukunj Co-operative Housing Society Limited

Mumbai City · Mishal Construction Private Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900006465

Delivery and registration

When is the project declared for completion?

Nehru Nagar Madhukunj Co-operative Housing Society Limited is registered with MahaRERA as P51900006465 and the promoter has declared completion for 31 Mar 2024.

31 Mar 2024

declared completion

30months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900006465
Registered on14 Aug 2017
Promoter-declared completion31 Mar 2024
Current statusCertificate Signed
Against todayabout 30 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Nehru Nagar Madhukunj Co-operative Housing Society Limited record 27 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 27 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Mishal Construction is the promoter of record on 16 projects registered with MahaRERA, 8 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

16projects

registered with MahaRERA

8flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Nehru Nagar Madhukunj Co-operative Housing Society Limited in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18.

BuildingWingsFloorsDeclared completion
Nehru Nagar Madhukunj Co-operative Housing Society Ltd1G+1831 Dec 2019

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for Nehru Nagar Madhukunj Co-operative Housing Society Limited, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019608118/02/2021POPATLAL DAYA CHHEDA vs MISHAL CONSTRUCTION PVT LTDorder passed
CC00600000019743208/07/2021DIPTI DATTA TAMGADGE vs M/S. MISHAL CONSTRUCTION PVT.LTD.order passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 4 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2020Due to change in Approval authority, draft development plan has come into force effecting from September 2018 and implementation on the same has been clarified by certain circulars
30 Dec 202031 Mar 2023Due to the ongoing pandemic in view of the outbreak of corona virus (Covid-19), restrictive activities were imposed in the city and the states. the process of approval has taken mo
31 Mar 202330 Sep 2023Covid
30 Sep 202331 Mar 2024Due to various reasons, such as delay in obtaining approvals, shortage of labour and materials, and impact of COVID-19 pandemic, the project could not be completed within the stipu

Location, Land & Connectivity

Located at Mumbai City, Mumbai City, 400024. Per the filed land record, the plot is bounded to the north by Bldg no 71 and 73, to the south by 40 feet wide road, to the east by Building No 72 74 and to the west by 60 feet wide road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)1 km
Chhatrapati Shivaji Int'l Airport3 km
Powai / Hiranandani business park7 km
Andheri MIDC / SEEPZ8 km
Lower Parel / Worli business district9 km
Nariman Point / Fort16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Mishal Construction Private Limited is the promoter on 12 MahaRERA-registered projects, of which 8 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Mishal Construction Private Limited project & its RERA track record →

Other flagged projects by Mishal Construction Private Limited

Mishal Construction Private Limited
Past its declared completion dateMumbai Suburban
Mishal Construction Private Limited
Not filing quarterly progress reportsMumbai Suburban
Mishal Construction Private Limited
Past its declared completion dateMumbai Suburban
Mishal Construction Private Limited
Past its declared completion dateMumbai Suburban
Mishal Construction Private Limited
Past its declared completion dateMumbai Suburban
Mishal Construction Private Limited
FlaggedMumbai Suburban

Other RERA-registered projects in Nehru Nagar

OM Nandadeep CO-OP. Hsg. Soc. LTD
possession by Oct 2026 · OM Nandadeep CO-OP Housing Society Limit
Ratnadeep Heights
possession by Oct 2026 · KRV Realty
Raghav Parijat
possession by Dec 2026 · Raghav Realty Developers
Hareshwar Pride
possession by Dec 2026 · Satyadeep Realtors Pvt. Ltd.
Nehru Nagar Nirmal C.h.s. Ltd
possession by Dec 2026 · Deraiya Realtors Private Limited
Nehru Nagar Shiv Vaibhav CHS LTD Bldg NO 38
possession by Dec 2026 · Parsn Construction AND Developers Privat

Other RERA-registered projects in Mumbai Suburban

Nehru Nagar Nirmal C.h.s. Ltd
possession by Dec 2026 · Deraiya Realtors Private Limited
Nehru Nagar Panchratna CHS Ltd, Bldg. No.5
declared completion Dec 2025 · Parsn Construction AND Developers Privat
Nehru Nagar Sangam Chsl
declared completion Dec 2023 · Priya Construction Company
Nehru Nagar Sharada CHS LTD Bldg NO. 62
declared completion Dec 2025 · Parsn Construction AND Developers Privat
Nehru Nagar Shiv Vaibhav CHS LTD Bldg NO 38
possession by Dec 2026 · Parsn Construction AND Developers Privat
Nehru Nagar Shree Ganesh Krupa CHS Ltd. Bldg NO. 120
declared completion Dec 2025 · Hiranimanthan Builders AND Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.