MahaRERA Property Intelligence · Mumbai Suburban

AVIARA

PM1180002500664 · Sahar · promoter Baluwala Builders

Certificate SignedDue 31 Dec 2031

Delivery & Registration

MahaRERA registrationPM1180002500664
Registered on26 Aug 2025
Promoter-declared completion31 Dec 2031
Current statusCertificate Signed
Against today65 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Construction Progress

MahaRERA's cost filing puts construction at ~21.0% of the estimated project cost incurred as of the last certificate (₹20.60 Cr spent against a ₹98.24 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 120 homes filed with MahaRERA, 53 are sold/booked (31 with registered agreements + 22 booked) and 67 remain available (~44% sold) — selling steadily. Buyers have committed ₹76.48 Cr in agreement value so far. Of that, ₹14.37 Cr (~19%) is already collected, ₹62.11 Cr receivable — a read on how far along these sales really are. Note: the project registers 268 homes in total, but this sold/unsold inventory filing covers only 120 of them — the other 148 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 53 registered agreements, the effective carpet rate is ₹23,974/sqft (typical range ₹17,965–₹25,729) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

⚠ The inventory filing also declares: 148 reserved. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11 and 268 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Sale Building1G+1196-
Composite Building1G+11172-

Unit mix on the filing: 261 residential and 7 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Sahar, Sahar Road, Mumbai, Mumbai Suburban, 400054. Per the filed land record, the plot is bounded to the north by Sahar Road, to the south by CTS No. 40, 42, to the east by P & T Colony and to the west by Laxmi Kameshwari CHSL. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport2 km
Andheri MIDC / SEEPZ3 km
Bandra Kurla Complex (BKC)4 km
Powai / Hiranandani business park5 km
Lower Parel / Worli business district12 km
Nariman Point / Fort20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Santacruz West

Woodstock Gardens
possession by Oct 2026 · Woodstock Realties Private Limited
Artteza
possession by Nov 2026 · Sunvision Estates
M.K Heritage
Not filing quarterly progress reports · possession by Dec 2026 · Shaista Majid Khan
Cyrilyn
possession by Dec 2026 · Not Available
JAY Krupa Sadan BY Shree Hari Realty
possession by Dec 2026 · Shree Hari Realty
Orchid Vasundhara
possession by Dec 2026 · Orchid Builtcon Pvt. Ltd.

Major developers building in Santacruz West

Other RERA-registered projects in Mumbai Suburban

Avighna
declared completion Dec 2023 · Gangar Infrastructure
Avighna CHS LTD
declared completion Oct 2024 · Majestic Royale Developers
Avighna Residency
declared completion Dec 2018 · Konark Shakti Group Of Companies
Avira Jewellery HUB
possession by Sep 2027 · Avira Realty Private Limited
Avira Sai Shreeji Co-Operative Housing Society Limited
possession by Dec 2029 · Avira Realty Private Limited
Avirahi Elegance
declared completion Jun 2025 · Abhigna Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026