MahaRERA · the public record
RAHEJA PARK WEST
SANTACRUZ WEST · GOKUL DEVELOPERS
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Dec 2026
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51800034035
Delivery and registration
When is the project declared for completion?
RAHEJA PARK WEST is registered with MahaRERA as P51800034035 and the promoter has declared completion for 31 Dec 2026.
31 Dec 2026
declared completion
3months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51800034035 |
| Registered on | 17 Mar 2022 |
| Promoter-declared completion | 31 Dec 2026 |
| Current status | Certificate Signed |
| Against today | 3 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RAHEJA PARK WEST record 18 quarterly progress reports since registration.
18quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).
Promoter record
What else is this promoter on record for?
Gokul Developers is the promoter of record on 31 projects registered with MahaRERA, 5 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
31projects
registered with MahaRERA
5flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for RAHEJA PARK WEST in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| RAHEJA PARK WEST | 1 | G+17 | 31 Dec 2026 |
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Location, Land & Connectivity
Located at SANTACRUZ WEST, 13.4 mtr wide DP Road, Andheri, Mumbai Suburban, 400054. Per the filed land record, the plot is bounded to the north by by property bearing Final Plot No s 83B8 83B9, to the south by by Existing 13 40 metre wide DP Road, to the east by Access Road being a part of plot bearing FPNO 83B9 and to the west by by property bearing Final Plot No 83B3. These are the boundaries as recorded in the filed land record.