Happy Home Residency CD

Unique Garden · Happy Home Residency

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700022362

Delivery and registration

When is the project declared for completion?

Happy Home Residency CD is registered with MahaRERA as P51700022362 and the promoter has declared completion for 30 Sep 2021.

30 Sep 2021

declared completion

60months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700022362
Registered on16 Sep 2019
Promoter-declared completion30 Sep 2021
Current statusCertificate Signed
Against todayabout 60 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Happy Home Residency CD record 9 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 9 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Happy Home Residency is the promoter of record on 149 projects registered with MahaRERA, 17 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

149projects

registered with MahaRERA

17flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Happy Home Residency CD in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
HAPPY HOME RESIDENCY WING C1G+1331 Mar 2020
HAPPY HOME RESIDENCY WIG D1G+1331 Mar 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Sep 2021We are in the process of obtaining the final Occupation Certificate from the Mira Bhayender Municipal Corporation and have performed all the acts as required by us, however given t

Location, Land & Connectivity

Located at Unique Garden, Off Kanakia Road, Thane, Thane, 401107. Per the filed land record, the plot is bounded to the north by D P Road, to the south by 436, to the east by 281 and to the west by 430. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Happy Home Residency is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Happy Home Residency

Happy Home Residency
FlaggedThane

Other RERA-registered projects in Mira Road East

Beaumonde
possession by Sep 2026 · Kanungo Property
Rassaz Greens Tower C D AND E
possession by Dec 2026 · Rassaz Infrastructure Private Limited
Coral
Deregistered by MahaRERA · possession by Dec 2026 · Nilesh Shantilal Tank
JP North Aviva
possession by Dec 2026 · JP Infra Realty Private Limited
Prithvi Sneh
Deregistered by MahaRERA · possession by Dec 2026 · Prithvi Buildworth Constructions
Shree RAM Heights
possession by Dec 2026 · Vavya Enterprises

Major developers building in Mira Road East

Other RERA-registered projects in Thane

Hare Krishna Janvi Height
declared completion Mar 2024 · Hare Krishna Group
Hari Heights
declared completion Dec 2019 · Nasim Niyaz Khan
Hari Krupa Residency, Kharde, Shahapur
declared completion Jul 2023 · Harikrupa Buildcon LLP
Hari Niwas
declared completion Jun 2024 · Hari Krishna Enterprise
Hari Shrushti
possession by Dec 2027 · Shrushti Creators
Hari Shrushti Wing A Phase II
possession by Dec 2030 · Shrushti Creators

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.