Mumbai/Project record

MahaRERA · the public record

Hari Om CHS Proposed

Andheri East · Hari Om Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800010174

Delivery and registration

When is the project declared for completion?

Hari Om CHS Proposed is registered with MahaRERA as P51800010174 and the promoter has declared completion for 31 Jul 2025.

31 Jul 2025

declared completion

14months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800010174
Registered on24 Aug 2017
Promoter-declared completion31 Jul 2025
Current statusCertificate Signed
Against todayabout 14 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Hari Om CHS Proposed record 33 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Hari Om CHS Proposed in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
Hari Dham II1G+1230 Jan 2022

Legal and disputes

What disputes are disclosed?

6 complaints are on the MahaRERA record for Hari Om CHS Proposed, with orders passed in 6 of them.

6complaints

6with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000000097304/10/2017Ashok Kumar Pasi vs Hari Om Developersorder passed
CC00600000007830801/03/2019ASGARI GINWALA vs HARI OM DEVELOPERSorder passed
CC00600000019719908/06/2021Asgari F Ginwala vs Hari Om Developersorder passed
CC00600000019811326/08/2021ABBAS YAKUB BALUWALA vs HARIOM DEVELOPERSorder passed
CC00600000019811426/08/2021ABBAS YAKUB BALUWALA vs HARIOM DEVELOPERSorder passed
CC00600000020937011/12/2021ALI AKBAR MANTRI vs HARIOM DEVELOPERSorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
City Civil Court22722014Add Intrim Relief

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Jul 2025Detail reason for delay of the project is uploaded in other documents.

Location, Land & Connectivity

Located at Andheri East, Magra, Andheri, Mumbai Suburban, 400069. Per the filed land record, the plot is bounded to the north by CTS NO 80, to the south by CTS NO 88, to the east by CTS NO 202 and to the west by CTS NO 81. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Andheri MIDC / SEEPZ1 km
Chhatrapati Shivaji Int'l Airport3 km
Powai / Hiranandani business park3 km
Bandra Kurla Complex (BKC)6 km
Lower Parel / Worli business district14 km
Nariman Point / Fort22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Hari Om Developers is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Hari Om Developers project & its RERA track record →

Other RERA-registered projects in Andheri East

Anamika
possession by Sep 2026 · NEW India Constructions
Romell Myra
Deregistered by MahaRERA · possession by Sep 2026 · Romell Properties Private Limited
Romell Orbis
possession by Sep 2026 · Romell Properties Private Limited
Amey Apartments
possession by Oct 2026 · Amey Realty AND Construction LLP
Elegant Residency
possession by Dec 2026 · Elegant Builders AND Developers
Girnar Residency Wing B Phase 1
possession by Dec 2026 · Nidhaan Realty LLP

Major developers building in Andheri East

Other RERA-registered projects in Mumbai Suburban

Hari Smruti CHS
declared completion Dec 2025 · Ramniyati Aditya Developers LLP
Harihareshwar SRA
possession by Dec 2027 · M/s Navnath Associates
Hariko Brahma
possession by Dec 2029 · Shree Parashnath
Harisharan Tattvaa
possession by Mar 2030 · Ashapura Reality Private Limited
Harmony
declared completion Aug 2026 · Shreenath Associates
Harshail Emerald Apartment
possession by Jan 2027 · Harshmaan Spaces LLP

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026