MahaRERA Property Intelligence · Palghar

HARSH APARTMENT

P99000014659 · KELVE ROAD · promoter Sai Sadguru Builders

Certificate SignedDue 30 Jun 2022

Delivery & Registration

MahaRERA registrationP99000014659
Registered on20 Dec 2017
Promoter-declared completion30 Jun 2022
Current statusCertificate Signed
Against todayabout 49 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sai Sadguru Builders is the promoter of record on 114 projects, of which 18 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
HARSH APARTMENT1G+630 Jun 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 202230 Dec 2021The reason for the request of project extension is mainly due to Covid-19 Pandemic. Because at that duration we can’t available the labours, materials and other required Essentials

Location, Land & Connectivity

Located at KELVE ROAD, KELVE ROAD, Vasai, Palghar, 401401. Per the filed land record, the plot is bounded to the north by GUT NO 193, to the south by GUT NO 144, to the east by GUT NO 1 and to the west by GUT NO 44. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~57 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ57 km
Powai / Hiranandani business park60 km
Chhatrapati Shivaji Int'l Airport62 km
Bandra Kurla Complex (BKC)64 km
Lower Parel / Worli business district71 km
Nariman Point / Fort79 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kelve East

Karrm Brahmaand Affordable Homes PVT LTD
Not filing quarterly progress reports · possession by Dec 2026 · Karrm Brahmaand Affordable Homes Private
Bhaskar Save Nagar
possession by Dec 2026 · Sai Builders And Developers
Radha Residency
possession by Dec 2026 · S. S. Enterprises
Rose Heights
possession by Dec 2026 · Mehandi Hasan Sarif Shalmani
Savera Complex
Not filing quarterly progress reports · possession by Dec 2026 · Savera Builders & Developers
Shree Ganesh Complex
possession by Dec 2026 · MSD Shivay Enterprise LLP

Other RERA-registered projects in Palghar

Haware Nakshatra Phase 2
declared completion Dec 2021 · Haware Infotech Ltd
Haware Nakshatra Phase 3
possession by Dec 2026 · Haware Infotech Ltd
Haware Nakshatra Phase 4
possession by Dec 2026 · Haware Infotech Ltd
Hayaat Centre
declared completion Mar 2018 · Hayaat Enterprises
Hayaat Galaxy
declared completion Dec 2021 · M M Enterprises
Hayaat Galaxy II
possession by Nov 2026 · M M Enterprises

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026