Mumbai/Project record

MahaRERA · the public record

HESTIA

Mumbai City · MAHENDRA KISAN SALUNKE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

25 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

25 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900006894

Delivery and registration

When is the project declared for completion?

HESTIA is registered with MahaRERA as P51900006894 and the promoter has declared completion for 25 Dec 2022.

25 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900006894
Registered on16 Aug 2017
Promoter-declared completion25 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for HESTIA record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 22 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Mahendra Kisan Salunke is the promoter of record on 72 projects registered with MahaRERA, 13 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

72projects

registered with MahaRERA

13flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for HESTIA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+43.

BuildingWingsFloorsDeclared completion
HESTIA1G+43-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court25772012Suit For Hearing

Location, Land & Connectivity

Located at Ward GSouth, Mumbai City, 400002. Per the filed land record, the plot is bounded to the north by 2084, to the south by 2087, to the east by 2070 AND SUBSTATION and to the west by J S S ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Nariman Point / Fort3 km
Lower Parel / Worli business district5 km
Bandra Kurla Complex (BKC)14 km
Chhatrapati Shivaji Int'l Airport16 km
Powai / Hiranandani business park20 km
Andheri MIDC / SEEPZ21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhuleshwar

Lifescapes Kshitij
Developer in insolvency (NCLT) · possession by Nov 2026 · Roxina Real Estate Pvt. Ltd.
Krishvi Escape
possession by Dec 2026 · Shagun Realty
Soutth Bay
possession by Dec 2026 · M/s. Sambhav Shelters
Ocean Drive
possession by Mar 2027 · Atul Projects GK Private Limited
Ajmera Downtown
possession by Dec 2027 · Ashjit Realties Pvt. Ltd.
Aryam
possession by Dec 2027 · Myra Infrastructure

Major developers building in Bhuleshwar

Other RERA-registered projects in Mumbai City

Hira Bhavan
declared completion Dec 2022 · Prem Satguru Constructions
Hira House
possession by Dec 2028 · Goshar Alliance LLP
Hitesh Heights
declared completion Dec 2023 · Sayed Mohamed Zahid
Hive Suites
possession by Jun 2027 · Shree Richa Realtors
Horizon Tower
declared completion Oct 2020 · Horizon Realty
Hubtown - Celeste
possession by Jul 2029 · Nayan Real Estate Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026