HS Emerald

Mulund East · HS Landmark LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

44units filed as unsoldInventory · 20 September 2026
31 Dec 2028declared completionMahaRERA registration · read 12 Jul 2026
144registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800079767

Delivery and registration

When is the project declared for completion?

HS Emerald is registered with MahaRERA as P51800079767 and the promoter has declared completion for 31 Dec 2028.

31 Dec 2028

declared completion

27months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800079767
Registered on26 Mar 2025
Promoter-declared completion31 Dec 2028
Current statusCertificate Signed
Against today27 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for HS Emerald record 5 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 5 quarterly progress reports on record since registration, with no current default.

Sales

How much has actually been sold?

In HS Emerald, 71 of 116 homes filed with MahaRERA are recorded as sold or booked, about 61%, and 45 remain available.

61%sold

71 of 116 homes

₹49.32 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹5.75 Cr (about 12%) is recorded as collected and ₹43.57 Cr as receivable. The project registers 144 homes in total, while this sold/unsold inventory filing covers 116 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 71 registered agreements, the effective carpet rate is ₹22,917/sqft, with eight in ten falling between ₹17,980 and ₹23,555 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 20 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 72 homes carry one, and 44 of the 116 are recorded unsold. Since we started watching this ledger, 4 homes have moved out of the unsold list, most recently on 11 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
203320 sqftRs 72.68 lakh typical, over Rs 53.00 lakh to Rs 80.49 lakh18 filed on this stack, floors 4–22

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In HS Emerald, 41 of the 44 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 43 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23 and 144 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Composite Building1G+23144-

Unit mix on the filing: 139 residential and 5 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Mulund East, V.B. Phadke Marg, Kurla, Mumbai Suburban, 400081. Per the filed land record, the plot is bounded to the north by Open Plot, to the south by Under Construction Building, to the east by 90 Feet Road and to the west by Anand CHS. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park8 km
Andheri MIDC / SEEPZ10 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)15 km
Lower Parel / Worli business district23 km
Nariman Point / Fort30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mulund East

Jagdale Giriraj
possession by Sep 2026 · Jagdale Infrastructure Pvt. Ltd.
Richmond Ananya
possession by Sep 2026 · Divine Enterprises
Mithagar Road Ekta Chsl
possession by Dec 2026 · Palan Realty Private Limited
Bimal Apartment Chsl
possession by Dec 2026 · Rite Builders & Developers
Govind Prakash SRA CHS LTD
possession by Dec 2026 · Omsai Developers
Jvms Monica Gardens
possession by Dec 2026 · JVM Spaces

Major developers building in Mulund East

Other RERA-registered projects in Mumbai Suburban

HS Heritage
possession by Mar 2029 · H.s.property Developers
HS Landmark
possession by Dec 2027 · H S Landmark
HS One
possession by Dec 2027 · HS Lifespace LLP
HS Pearl
declared completion Dec 2024 · HS Property Developers
HS Spring
declared completion Dec 2024 · Ashta Siddhi Constructions Private Limit
Hubtown Premiere Residences - Bel Air
declared completion Jul 2026 · Hubtown Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026