Hundiwale

P51700046290 · Chendani · promoter Aditya Associates

Certificate SignedDue 16 Sep 2023

Delivery & Registration

MahaRERA registrationP51700046290
Registered on20 Jun 2022
Promoter-declared completion16 Sep 2023
Current statusCertificate Signed
Against todayabout 34 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
Hundiwale1G+716 Sep 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
16 Sep 202331 Mar 2024Construction work got delayed from the contractors end and also there was a delay from vendors in supplying certain construction materials. However inspite of the above, work on si

Location, Land & Connectivity

Located at Chendani, Ganesh Purushottam Rai Road, Thane, Thane, 400603. Per the filed land record, the plot is bounded to the north by 6 Meters Wide Road, to the south by Anand Bhuvan Building, to the east by Mirani Nagar and to the west by Jalaram Store. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~10 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park10 km
Andheri MIDC / SEEPZ12 km
Chhatrapati Shivaji Int'l Airport15 km
Bandra Kurla Complex (BKC)17 km
Lower Parel / Worli business district26 km
Nariman Point / Fort33 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Aditya Associates is the promoter on 12 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Aditya Associates project & its RERA track record →

Other flagged projects by Aditya Associates

Other RERA-registered projects in Kopri

Amar Pushpakunj
possession by Jul 2026 · Avighna Redevelopers
Sujan CO-OP. Hsg. Soc. LTD
possession by Aug 2026 · Joshi AND Vishwas Realtors LLP
Viraj Heights
possession by Dec 2026 · V-RAJ Buildcon
Amogh Ratan
possession by Dec 2026 · Aashish Krishanarao Pathare
Royal Height - Building B
possession by Dec 2026 · New Royal Construction Company.
Ajita CO-Operative Housing Society Limited
possession by Mar 2027 · Govind Ojass Edifice Pvt. Ltd.

Other RERA-registered projects in Thane

Hussain Excellency
possession by Dec 2030 · LIS India Construction Company PVT LTD
Hyde Park Residency F1 Building Phase
declared completion Dec 2023 · Nexus Builders AND Developers PVT LTD
Hyde Park Residency F4 Building Phase
declared completion Dec 2021 · Nexus Builders AND Developers PVT LTD
Hyde Park Residency F5 Building Phase
declared completion Sep 2023 · Nexus Builders AND Developers PVT LTD
Hyde Park Residency F6 Building Phase
declared completion Dec 2021 · Nexus Builders AND Developers PVT LTD
I.p.royal Villa
declared completion Apr 2025 · Aslam Ismail Patel

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026