Mumbai/Project record

MahaRERA · the public record

Deepjyoti Co. Op. Housing Society

Naupada · Aditya Associates

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

20units filed as unsoldInventory · 20 September 2026
31 Jan 2028declared completionMahaRERA registration · read 12 Jul 2026
47registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jan 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PR1330002500870

Delivery and registration

When is the project declared for completion?

Deepjyoti Co. Op. Housing Society is registered with MahaRERA as PR1330002500870 and the promoter has declared completion for 31 Jan 2028.

31 Jan 2028

declared completion

16months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationPR1330002500870
Registered on22 Sep 2025
Promoter-declared completion31 Jan 2028
Current statusCertificate Signed
Against today16 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Deepjyoti Co. Op. Housing Society record 5 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Construction

How much construction cost has been reported?

In Deepjyoti Co. Op. Housing Society, ₹36,100 of a declared ₹12.38 Cr estimated project cost is reported as incurred, about 0.0%, as at the last certified filing with MahaRERA.

0.0%

₹36,100

of ₹12.38 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In Deepjyoti Co. Op. Housing Society, 0 of 20 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 20 remain available.

0%sold

0 of 20 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. The project registers 47 homes in total, while this sold/unsold inventory filing covers 20 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 1101974 sqft (90.48 sqm)₹1.48 Cr
Floor 1102712 sqft (66.14 sqm)₹1.09 Cr
Floor 1103918 sqft (85.27 sqm)₹1.40 Cr
Floor 11041,243 sqft (115.45 sqm)₹2.02 Cr
Floor 2201974 sqft (90.48 sqm)₹1.48 Cr
Floor 2202712 sqft (66.14 sqm)₹1.09 Cr
Floor 22041,243 sqft (115.45 sqm)₹2.02 Cr
Floor 2206780 sqft (72.48 sqm)₹1.23 Cr
Floor 3301974 sqft (90.48 sqm)₹1.48 Cr
Floor 3302712 sqft (66.14 sqm)₹1.09 Cr
Floor 4402712 sqft (66.14 sqm)₹1.09 Cr
Floor 44041,243 sqft (115.45 sqm)₹2.02 Cr
Floor 5502712 sqft (66.14 sqm)₹1.15 Cr
Floor 55041,333 sqft (123.85 sqm)₹2.26 Cr
Floor 5506846 sqft (78.62 sqm)₹1.40 Cr
Floor 6602712 sqft (66.14 sqm)₹1.15 Cr
Floor 66041,333 sqft (123.85 sqm)₹2.26 Cr
Floor 77011,039 sqft (96.53 sqm)₹1.73 Cr
Floor 7702547 sqft (50.83 sqm)₹1.07 Cr
Floor 7705528 sqft (49.06 sqm)₹85.83 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Deepjyoti Co. Op. Housing Society in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 20 September 2026

What the filings record, home by home

Read from MahaRERA on 20 September 2026

No home in Deepjyoti Co. Op. Housing Society carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 20 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 16,114 a sq ft typical, over Rs 15,243 to Rs 19,479.

A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.

The Reckoner Record lists all 20 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.

See all 20 filed valuations — ₹999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8 and 47 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Deepjyoti Co. Op. Housing Society1G+847-

Unit mix on the filing: 47 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Naupada, Veer Savarkar Path, Thane, Thane, 400602. Per the filed land record, the plot is bounded to the north by Indu Moni (162 A) adjacent to it is access to 18 mtr. road, to the south by Cross Villa, to the east by Apsara Rangashree and to the west by Cross Villa. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park11 km
Andheri MIDC / SEEPZ13 km
Chhatrapati Shivaji Int'l Airport16 km
Bandra Kurla Complex (BKC)18 km
Lower Parel / Worli business district26 km
Nariman Point / Fort34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Aditya Associates is the promoter on 12 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Aditya Associates project & its RERA track record →

Other flagged projects by Aditya Associates

Other RERA-registered projects in Naupada

Ashtavinayak Residency
possession by Sep 2026 · Ashvattha Realty LLP
Shree Krupa CO OP Housing Society
possession by Sep 2026 · Sharda Vastu Nirmitee Pvt. Ltd.
Ashirwad Co-Operative Housing Society Ltd
possession by Oct 2026 · Padmanabh Developers
Platinum Square
possession by Oct 2026 · Ratnamani Buildcon
Om Yashodhan Chsl
possession by Nov 2026 · Silver Stone Realty
Larkins 315 FIO-A
possession by Dec 2026 · M/S Pushpak Developers

Major developers building in Naupada

Other RERA-registered projects in Thane

Deepmala CHS LTD
possession by Dec 2027 · S. D. Bhalerao Associates
Deepraj Residency
declared completion Dec 2019 · Deepraj Enterprises
Deepsamay CHS
possession by Jun 2028 · Shree Samarth Enterprises
Delta Avenue
declared completion Dec 2018 · Delta Realtors
Delta Greenville - Aster
possession by Jan 2031 · Delta Synergy LLP
Delta Greenville - Cedar
possession by Dec 2030 · Delta Synergy LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026