Mumbai/Project record

MahaRERA · the public record

Phatak Wada

Tembhi Naka · Aditya Associates

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

18units filed as unsoldInventory · 19 September 2026
30 Jun 2025declared completionMahaRERA registration · read 12 Jul 2026
58registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700049073

Delivery and registration

When is the project declared for completion?

Phatak Wada is registered with MahaRERA as P51700049073 and the promoter has declared completion for 30 Jun 2025.

30 Jun 2025

declared completion

15months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700049073
Registered on30 Jan 2023
Promoter-declared completion30 Jun 2025
Current statusCertificate Signed
Against todayabout 15 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Phatak Wada record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Sales

How much has actually been sold?

In Phatak Wada, 9 of 27 homes filed with MahaRERA are recorded as sold or booked, about 33%, and 18 remain available.

33%sold

9 of 27 homes

₹8.22 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹4.22 Cr (about 51%) is recorded as collected and ₹0 as receivable. The project registers 58 homes in total, while this sold/unsold inventory filing covers 27 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 9 registered agreements, the effective carpet rate is ₹9,708/sqft, with eight in ten falling between ₹9,228 and ₹22,939 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 1B-102564 sqft (52.39 sqm)₹64.70 Lakh
Floor 1B-103410 sqft (38.13 sqm)₹48.00 Lakh
Floor 2A-201604 sqft (56.11 sqm)₹60.48 Lakh
Floor 2A-203671 sqft (62.31 sqm)₹59.91 Lakh
Floor 2A-2041,051 sqft (97.65 sqm)₹92.41 Lakh
Floor 2B-201574 sqft (53.32 sqm)₹51.65 Lakh
Floor 3A-3041,051 sqft (97.65 sqm)₹92.41 Lakh
Floor 3B-301574 sqft (53.32 sqm)₹51.65 Lakh
Floor 3B-303443 sqft (41.18 sqm)₹40.48 Lakh
Floor 3B-304461 sqft (42.81 sqm)₹41.98 Lakh
Floor 4A-4041,051 sqft (97.65 sqm)₹92.41 Lakh
Floor 4B-402533 sqft (49.53 sqm)₹48.16 Lakh
Floor 4B-403443 sqft (41.18 sqm)₹40.48 Lakh
Floor 5B-501574 sqft (53.32 sqm)₹54.23 Lakh
Floor 6A-6041,051 sqft (97.65 sqm)₹97.03 Lakh
Floor 7B-701574 sqft (53.32 sqm)₹51.48 Lakh
Floor 7B-703443 sqft (41.18 sqm)₹42.51 Lakh
Ground/Floor 0Office No. 1233 sqft (21.61 sqm)₹46.93 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 19 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 9 homes carry one, and 18 of the 27 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
B-402533 sqftRs 50.00 lakh2 filed on this stack, floors 3–5

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In Phatak Wada, 1 of the 18 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 17 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8 and 58 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Phatak Wada1G+858-

Unit mix on the filing: 49 residential and 9 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Tembhi Naka, old Thane Pune Road, Thane, Thane, 400601. Per the filed land record, the plot is bounded to the north by Wadia Hospital, to the south by Vishal Building, to the east by Veer Savarkar Road and to the west by B J High School. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park12 km
Andheri MIDC / SEEPZ13 km
Chhatrapati Shivaji Int'l Airport17 km
Bandra Kurla Complex (BKC)18 km
Lower Parel / Worli business district27 km
Nariman Point / Fort34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Aditya Associates is the promoter on 12 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Aditya Associates project & its RERA track record →

Other flagged projects by Aditya Associates

Other RERA-registered projects in Thane

Avesa
possession by Oct 2026 · Jagdale Infrastructure Pvt. Ltd.
Ramashankar CHS LTD
possession by Oct 2026 · SAI Prasad Builders AND Developers
Bhavana Apartment CHS
possession by Nov 2026 · Shree Infra
Sheth Zuri
possession by Dec 2026 · Sheth Developers Private Limited
Musica Apartment
possession by Dec 2026 · E I Construction
Rustomjee LA Familia - Wing A
possession by Dec 2026 · Kapstone Constructions Private Limited

Major developers building in Thane

Other RERA-registered projects in Thane

Phoenix Aura Phase 2
possession by Jan 2027 · Phoenix Buildcon
Pimpladevi Construction
declared completion Apr 2025 · Pimpladevi Construction Sunilkumar C Sah
Pineshire
declared completion Dec 2025 · Aanya Residences
Pink City Trident Phase 2
declared completion Apr 2022 · AMI Infra
Pinnacle Structures
possession by Mar 2030 · Not Available
Pinnacle Vatika
possession by Dec 2029 · MM Pinnacle Buildcon LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026