31 Mar 2033declared completionMahaRERA registration · read 02 Jul 2026
261registered unitsMahaRERA registration · read 02 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 02 Jul 2026

The record · free to read

Registration read 02 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2033

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 02 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PR1171012502413

Delivery and registration

When is the project declared for completion?

Imperial T3 Wing C is registered with MahaRERA as PR1171012502413 and the promoter has declared completion for 31 Mar 2033.

31 Mar 2033

declared completion

78months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 02 Jul 2026

MahaRERA registrationPR1171012502413
Registered on20 Feb 2026
Promoter-declared completion31 Mar 2033
Current statusCertificate Signed
Against today78 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Imperial T3 Wing C record 2 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 02 Jul 2026

  • Filing progress reports — 2 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Corporation Private Limited is the promoter of record on 23 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

23projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 02 Jul 2026

Construction

How much construction cost has been reported?

In Imperial T3 Wing C, ₹11.18 Cr of a declared ₹1970.69 Cr estimated project cost is reported as incurred, about 0.6%, as at the last certified filing with MahaRERA.

0.6%

₹11.18 Cr

of ₹1970.69 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 02 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Imperial T3 Wing C in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 02 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+93 and 261 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Wing-C1G+93261-

Unit mix on the filing: 261 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 3 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High Court254682025Ongoing
Bombay High Court395642025Ongoing
High Court16632026Ongoing

Location, Land & Connectivity

Located at Tardeo, B B Nakashe Marg, Mumbai City, Mumbai City, 400034. Per the filed land record, the plot is bounded to the north by Rehab Residential Building no 8 & 9 , to the south by Sale Residential buildings wing A & B by name Imperial Tower, to the east by plot bearing CS No. 725(pt) & 4/725(pt) and to the west by Khamballa Hill on plot bearing CS No. 4/723, 3A/723, 8/823. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Lower Parel / Worli business district4 km
Nariman Point / Fort5 km
Bandra Kurla Complex (BKC)12 km
Chhatrapati Shivaji Int'l Airport14 km
Andheri MIDC / SEEPZ19 km
Powai / Hiranandani business park19 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every S. D. Corporation Private Limited project & its RERA track record →

Other RERA-registered projects in Tardeo

Stardeous
possession by Dec 2027 · Heston Builders PVT LTD
The Altitude
possession by Mar 2029 · VDV Infrastructures LLP
Kinjal Legacy
possession by Jun 2029 · Hi Rock Construction Private Limited
The Imperial I
possession by Dec 2029 · SDC Township Private Limited
Ayuddha Eved
possession by Dec 2030 · Crystal Progressive LLP
Raheja Sobo Residences
possession by Jul 2033 · K Raheja Corp Real Estate Private Limite

Other RERA-registered projects in Mumbai City

Imperial T3 Wing C1
possession by Jul 2034 · S D Corporation Private Limited
Inara
possession by Dec 2026 · M/S S Square Construction
Indiabulls Sky Forest -A3
declared completion Sep 2023 · Indiabulls Properties Private Limited
Indu Villa
declared completion Mar 2019 · Narendra Vasanji Furia
Infinity Residences
possession by Dec 2028 · Infinity Associates
Innovative Icon
possession by Mar 2027 · Innovative Realest Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026