INDIAN OCEAN WING C

P51800010364 · promoter Cordcon Builders Pvt

Certificate SignedDue 30 Mar 2022

Delivery & Registration

MahaRERA registrationP51800010364
Registered on24 Aug 2017
Promoter-declared completion30 Mar 2022
Current statusCertificate Signed
Against todayabout 52 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Cordcon Builders Pvt is the promoter of record on 2 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
INDIAN OCEAN WING C1G+16-

Complaints & Orders

2 complaints are on the MahaRERA record for this project, with orders passed in 2. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000001277506/01/2018ARPANA PANDYA vs Mr Tajdin Mohammed Marediaorder passed
CC00600000010029716/08/2019MRS. RASHIQUAH SHAKEEL AND MR. SHAKEEL AHMAD vs CORDCON BUILDERS PRIVATE LIMITEDorder passed

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400058. Per the filed land record, the plot is bounded to the north by GILBERT HILL, to the south by CARIBBEAN, to the east by V P ROAD and to the west by INDIAN OCEAN A B. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Andheri MIDC / SEEPZ3 km
Chhatrapati Shivaji Int'l Airport4 km
Bandra Kurla Complex (BKC)7 km
Powai / Hiranandani business park7 km
Lower Parel / Worli business district14 km
Nariman Point / Fort22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Andheri West

Shepherd Horizon
possession by Jul 2026 · Goodbuild India Private Limited
Anutam
possession by Sep 2026 · Truly Highdreams Realtors LLP
Vivan Homes
possession by Dec 2026 · Imprint Estates Pvt Ltd
Alpine Primo
possession by Dec 2026 · Alpine Infraheights LLP
Bella Casa
possession by Dec 2026 · Konark Bella Casa LLP
Hetali Sagar
possession by Dec 2026 · Jayesh Himatlal Pandya

Major developers building in Andheri West

Other RERA-registered projects in Mumbai Suburban

Indra Dhanush
declared completion Mar 2025 · AUM Serenity
Indu Ganesh Heights
declared completion Dec 2020 · Tigon Reality Private Limited
Indu Smruti CHS Ltd
possession by Dec 2028 · Indu Smruti CHS Ltd
Indus
declared completion Dec 2022 · Satre Infrastructure Pvt. Ltd.
Infina Gardens
declared completion May 2020 · Infina Ashapura Homes LLP
Infinity Elements
declared completion Dec 2024 · Maharani Estate

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026