Mumbai/Project record

MahaRERA · the public record

INDIAN OCEAN WING C

Mumbai Suburban · CORDCON BUILDERS PVT LTD

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Mar 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Mar 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800010364

Delivery and registration

When is the project declared for completion?

INDIAN OCEAN WING C is registered with MahaRERA as P51800010364 and the promoter has declared completion for 30 Mar 2022.

30 Mar 2022

declared completion

54months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800010364
Registered on24 Aug 2017
Promoter-declared completion30 Mar 2022
Current statusCertificate Signed
Against todayabout 54 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for INDIAN OCEAN WING C record 19 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 19 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Cordcon Builders is the promoter of record on 2 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for INDIAN OCEAN WING C in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
INDIAN OCEAN WING C1G+16-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for INDIAN OCEAN WING C, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000001277506/01/2018ARPANA PANDYA vs Mr Tajdin Mohammed Marediaorder passed
CC00600000010029716/08/2019MRS. RASHIQUAH SHAKEEL AND MR. SHAKEEL AHMAD vs CORDCON BUILDERS PRIVATE LIMITEDorder passed

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400058. Per the filed land record, the plot is bounded to the north by GILBERT HILL, to the south by CARIBBEAN, to the east by V P ROAD and to the west by INDIAN OCEAN A B. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Andheri MIDC / SEEPZ3 km
Chhatrapati Shivaji Int'l Airport4 km
Bandra Kurla Complex (BKC)7 km
Powai / Hiranandani business park7 km
Lower Parel / Worli business district14 km
Nariman Point / Fort22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Andheri West

Anutam
possession by Sep 2026 · Truly Highdreams Realtors LLP
Vivan Homes
possession by Dec 2026 · Imprint Estates Pvt Ltd
Alpine Primo
Registration suspended · possession by Dec 2026 · Alpine Infraheights LLP
Bella Casa
possession by Dec 2026 · Konark Bella Casa LLP
Hetali Sagar
possession by Dec 2026 · Jayesh Himatlal Pandya
La Alteza
possession by Dec 2026 · Emerald Developers

Major developers building in Andheri West

Other RERA-registered projects in Mumbai Suburban

Infina Gardens
declared completion May 2020 · Infina Ashapura Homes LLP
Infinity Tower
possession by Dec 2030 · M/s. Rassaz Infrastructure Private Limit
Insignia
declared completion Dec 2024 · Shreepati Rise Estate LLP
Insignia
possession by Dec 2026 · Two Taurus Realty LLP
Inspira Aura
possession by Mar 2029 · IR JPV Estates Pvt. Ltd.
Inspira ONE
possession by Jun 2030 · Inspira Buildcon Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026