Mumbai/Project record

MahaRERA · the public record

INSIGNIA

Dadar West · Ashwatha Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900012105

Delivery and registration

When is the project declared for completion?

INSIGNIA is registered with MahaRERA as P51900012105 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900012105
Registered on01 Sep 2017
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for INSIGNIA record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 30 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for INSIGNIA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+55.

BuildingWingsFloorsDeclared completion
INSIGNIA1G+55-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for INSIGNIA, with orders passed in 1 of them.

2complaints

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019488321/11/2020Smt. Bhavna Hasmukh Gogri vs Hemant Nanji Chhedaorder passed
CC1250025524/01/2025PURVI AMIT THAKKAR vs Ashwatha Developerspending / no order on file

Legal & Litigation

The promoter has declared 8 court cases on this project to MahaRERA. 6 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court17312009Disposed
City Civil Court14052010Pending
City Civil Court31072014Pending
Bombay High Court23212016Pending
Bombay High Court23192016Pending
Bombay High Court27312016Pending
Supreme Court Of India240442014Pending
High Court Of Bombay1162012Disposed

Location, Land & Connectivity

Located at Dadar West, S.K. Bole Road, Ward GNorth, Mumbai City, 400028. Per the filed land record, the plot is bounded to the north by FP NO 260, to the south by FP NO 269, to the east by FP NO 265 and to the west by FP NO 259. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Lower Parel / Worli business district3 km
Bandra Kurla Complex (BKC)6 km
Chhatrapati Shivaji Int'l Airport8 km
Nariman Point / Fort11 km
Andheri MIDC / SEEPZ13 km
Powai / Hiranandani business park13 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dadar West

Arihant Tower
possession by Sep 2026 · Mehta Developers
Palette
possession by Sep 2026 · Suraj Estate Developers LTD
Vijayshree
possession by Sep 2026 · Sugee Eighteen Developers LLP
Yash Trinity
possession by Sep 2026 · Bhalchandra Vinayak Wadnerkar
Sugee Sukrut
possession by Oct 2026 · Sugee Nine Developers LLP
1891 Ekam Parkk
possession by Dec 2026 · Nascent Developers

Major developers building in Dadar West

Other RERA-registered projects in Mumbai City

Inspire
possession by Sep 2026 · R K Constructions
Island Cove
possession by Dec 2028 · LH Residential Housing Private Limited
Island Cove Tower 3
possession by Dec 2029 · LH Residential Housing Private Limited,
Island Cove Tower 4
possession by Dec 2030 · LH Residential Housing Private Limited,
J K Apartment
possession by Dec 2026 · Plus Properties PVT LTD
Jade Acharya
possession by Dec 2026 · Raghavendra Acharya & Others

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026