IPSIT NAVODAY PHASE 3

PALGHAR · IPSIT ENTERPRISE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jan 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jan 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000011851

Delivery and registration

When is the project declared for completion?

IPSIT NAVODAY PHASE 3 is registered with MahaRERA as P99000011851 and the promoter has declared completion for 30 Jan 2022.

30 Jan 2022

declared completion

56months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000011851
Registered on31 Aug 2017
Promoter-declared completion30 Jan 2022
Current statusCertificate Signed
Against todayabout 56 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for IPSIT NAVODAY PHASE 3 record 19 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 19 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Ipsit Enterprise is the promoter of record on 10 projects registered with MahaRERA, 5 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

10projects

registered with MahaRERA

5flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for IPSIT NAVODAY PHASE 3 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
IPSIT NAVODAY PHASE 3 BUILDING NO 11G+531 Aug 2018
IPSIT NAVODAY PHASE 3 BUILDING NO 21G+531 Aug 2018

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for IPSIT NAVODAY PHASE 3, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000005571928/09/2018SHANTARAM SHANKAR VEDAK vs HARSHA REALTORS PVT LTDorder passed
CC00600000021042117/03/2022SHANTARAM SHANKAR VEDAK vs M/s HARSHA REALTORS PVT LTDorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Jan 2021Shortage of sand and raw material which was beyond our control. Requesting you to grant extension till 31-03-2019.
31 Jan 202131 Jan 2021Due to shortage of material and bank crises we were not able to complete the project on given deadline. we would like to request you to grant us extension till 31/01/2021

Location, Land & Connectivity

Located at PALGHAR, OFF OLD SATIPATI MARG, Borivali, Mumbai Suburban, 401404. Per the filed land record, the plot is bounded to the north by BUILDING NO 3 AND 4 OF 4TH PHASE, to the south by NORTH VILLAGE ROAD, to the east by INTERNAL LAYOUT ROAD and to the west by S NO 995. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~63 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ63 km
Powai / Hiranandani business park66 km
Chhatrapati Shivaji Int'l Airport68 km
Bandra Kurla Complex (BKC)70 km
Lower Parel / Worli business district77 km
Nariman Point / Fort85 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Ipsit Enterprise is the promoter on 8 MahaRERA-registered projects, of which 4 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Ipsit Enterprise project & its RERA track record →

Other flagged projects by Ipsit Enterprise

Ipsit Enterprise
Not filing quarterly progress reportsPalghar
Ipsit Enterprise
Past its declared completion datePalghar
Ipsit Enterprise
Past its declared completion datePalghar

Other RERA-registered projects in Palghar

Parasnath Garden- SNO 200-1-2
possession by Sep 2026 · Shreenath Enterprises
SA Heights
possession by Sep 2026 · Atul Kumar Tripathi
SAI Park
possession by Sep 2026 · OM Siddhivinayak Developers
Shiv Krupa
possession by Oct 2026 · Shivaay Realty
V Square Arcade
possession by Oct 2026 · V Square
Nisarg Shrushti Phase-2
possession by Nov 2026 · Arvel Realtors

Major developers building in Palghar

Other RERA-registered projects in Palghar

Ipsit Navoday Phase 5
declared completion Jun 2024 · Ipsit Enterprise
Ipsit Paradise Phase 2
declared completion Apr 2026 · Dreamland Developers
Ipsit Sukhanand
possession by Dec 2027 · Incline Realtors
IRA Forming Part OF THE Complex Akhand
possession by Dec 2027 · Techton Lifespaces LLP
Irasa Park Phase 1
possession by Dec 2027 · Suburban Spaces LLP
ISA Forming THE Part OF Complex Akhand
possession by Jun 2028 · Techton Lifespaces LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026