Mumbai/Project record

MahaRERA · the public record

LANDMARK 2

Mumbai Suburban · IPSIT ENTERPRISE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000003878

Delivery and registration

When is the project declared for completion?

LANDMARK 2 is registered with MahaRERA as P99000003878 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000003878
Registered on06 Aug 2017
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for LANDMARK 2 record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 30 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Ipsit Enterprise is the promoter of record on 10 projects registered with MahaRERA, 5 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

10projects

registered with MahaRERA

5flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for LANDMARK 2 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2.

BuildingWingsFloorsDeclared completion
BUNGALOW A1 - A1G+231 Dec 2018
BUNGALOW NO 21G+131 Dec 2018
BUNGALOW NO 31G+131 Dec 2018
BUNGALOW NO 41G+1-
BUNGALOW NO 51G+1-
BUNGALOW NO 61G+1-
BUNGALOW NO 71G+1-
BUNGALOW NO 81G+1-
BUNGALOW NO 91G+1-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2023DUE TO SHORTAGE OF MATERIAL AND BANK CRISES THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD REQUEST YOU TO KINDLY GRANT US EXTENSION FURTHER TLL 31-12-2023. REQUEST YOU

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 401404. Per the filed land record, the plot is bounded to the north by INTERNAL LAYOUT ROAD, to the south by G NO 993 PT, to the east by G NO 993 PT and to the west by INTERNAL LAYOUT ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~63 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ63 km
Powai / Hiranandani business park66 km
Chhatrapati Shivaji Int'l Airport68 km
Bandra Kurla Complex (BKC)70 km
Lower Parel / Worli business district77 km
Nariman Point / Fort85 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Ipsit Enterprise is the promoter on 8 MahaRERA-registered projects, of which 4 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Ipsit Enterprise project & its RERA track record →

Other flagged projects by Ipsit Enterprise

Ipsit Enterprise
Not filing quarterly progress reportsPalghar
Ipsit Enterprise
Past its declared completion datePalghar
Ipsit Enterprise
Past its declared completion datePalghar

Other RERA-registered projects in Palghar

Parasnath Garden- SNO 200-1-2
possession by Sep 2026 · Shreenath Enterprises
SA Heights
possession by Sep 2026 · Atul Kumar Tripathi
SAI Park
possession by Sep 2026 · OM Siddhivinayak Developers
Shiv Krupa
possession by Oct 2026 · Shivaay Realty
V Square Arcade
possession by Oct 2026 · V Square
Nisarg Shrushti Phase-2
possession by Nov 2026 · Arvel Realtors

Major developers building in Palghar

Other RERA-registered projects in Palghar

Landmark Plaza
possession by Dec 2026 · Imran Haji Yusuf Jummani
Lavanya Apartment
declared completion Jan 2024 · Royal Infra
Laxmi APT
declared completion Dec 2023 · Rameshchandra Ramnidh Pandey
Laxmi Developers
declared completion Jul 2022 · Laxmi Developers
Laxmi Heights
possession by Dec 2027 · Janavi Builders & Developers
Laxmi Tower
possession by Dec 2030 · Shree Construction

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.