MahaRERA Property Intelligence · Raigarh

JAGUAR HEIGHTS

P52000047363 · VADGHAR · promoter Rupesh Machhindranath Dhumal

Certificate SignedDue 31 Dec 2024

Delivery & Registration

MahaRERA registrationP52000047363
Registered on27 Oct 2022
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Rupesh Machhindranath Dhumal is the promoter of record on 3 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
JAGUAR HEIGHTS1G+1228 Feb 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
28 Feb 202431 Dec 2024Due to some clearance and permission of our project from cidco authority, the construction of the projects took time,

Location, Land & Connectivity

Located at VADGHAR , PLOT NO 81 SECTOR R4 PUSHPAK NODE VADGHAR , Panvel, Raigarh, 410206. Per the filed land record, the plot is bounded to the north by PLOT NO 68 67A, to the south by 11 MTR WIDE ROAD, to the east by 9 MTR WIDE ROAD and to the west by PLOT NO 80. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~25 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park25 km
Bandra Kurla Complex (BKC)25 km
Chhatrapati Shivaji Int'l Airport27 km
Lower Parel / Worli business district28 km
Andheri MIDC / SEEPZ29 km
Nariman Point / Fort29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Panvel

Ambaji Residency
possession by Jul 2026 · Vishal Tukaram Patil
Bayview
possession by Jul 2026 · Skyline Realbuild LLP
Delta Heights
possession by Jul 2026 · Shreenathji Organisers Pvt. Ltd.
Micron Residency
possession by Jul 2026 · Micron Infra
Shree Mahadev Residency
possession by Jul 2026 · SK Developers
Aishwarya Cooperative Housing Society
possession by Aug 2026 · Royal Enterprises

Major developers building in Panvel

Other RERA-registered projects in Raigarh

JAI Balaji
declared completion Feb 2019 · Varsha Rakesh Sutar
JAI Ganesh
declared completion Jul 2022 · Atharv Construction And Developers
Jai Ganesh Sapphire
possession by Dec 2026 · Hezal Infrastructure
Jai Ganesh Vishnu Bliss
declared completion Dec 2025 · Varuna Ashok Mewani
JAI Heritage
possession by Dec 2026 · Wings Buildcon
JAI Malhar Apartment
declared completion Mar 2022 · Gajanan Shyamrao Khabale

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026