JAI GOPI KRISHNA CHS LTD

DEONAR · VVA REALITY

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800001769

Delivery and registration

When is the project declared for completion?

JAI GOPI KRISHNA CHS LTD is registered with MahaRERA as P51800001769 and the promoter has declared completion for 31 Dec 2018.

31 Dec 2018

declared completion

93months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800001769
Registered on29 Jul 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 93 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for JAI GOPI KRISHNA CHS LTD record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for JAI GOPI KRISHNA CHS LTD in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2.

BuildingWingsFloorsDeclared completion
JAI GOPI KRISHNA CHS LTD SCHOOL PLOT1G+231 Dec 2017

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High Court104 OF 20152015Consent Terms Filed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2018JaI Gopi Krishna Chs Ltd and M/s. Nav Durga Construction Company(NDC) entered into Development Agreement dated 6th January 2007, registered under serial No. BDR/-13-208 of 2007.Pla

Location, Land & Connectivity

Located at DEONAR, GOVANDI STATION ROAD, Kurla, Mumbai Suburban, 400088. Per the filed land record, the plot is bounded to the north by BY LAND CTS NO 300 BELONGING TO DOCK LABOUR BOARD, to the south by BY LAN BEARING SURVEY NO 89 PT AND CTS 315, to the east by BY LAND BEARING SURVEY NO 89 PART AND CTS 315 and to the west by BY LAND BEARING CTS NO 307 BELONGING TO BHOITE FAM. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Bandra Kurla Complex (BKC)7 km
Chhatrapati Shivaji Int'l Airport8 km
Powai / Hiranandani business park8 km
Andheri MIDC / SEEPZ11 km
Lower Parel / Worli business district12 km
Nariman Point / Fort18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Deonar

Surve Tower
possession by Dec 2026 · Meena Vikas Raikar
Gagan Giri Co-Operative Housing Society Limited
Not filing quarterly progress reports · possession by Dec 2026 · Mishal Construction Private Limited
Akshar Amar Mansion
possession by Mar 2027 · Akshar Properties
Anuvidnyan Nagar Co-Op. Housing Society Ltd
possession by Jun 2027 · Makwise Homes LLP
Purva Clermont Wing A
possession by Jun 2027 · Puravankara Limited
Purva Clermont Wing B
possession by Jun 2027 · Puravankara Limited

Major developers building in Deonar

Other RERA-registered projects in Mumbai Suburban

Jai Kamal
declared completion Aug 2026 · Ameet Infra
JAI Savitri CHS LTD
declared completion Sep 2024 · A&a Aristocrat Realty Private Limite
JAI Shreeram Prasanna Chsl
declared completion Aug 2026 · Riyaz Ramzan Shah
JAI Swami Krupa Building
declared completion Dec 2025 · Maitri AND Maitri Realtors
JAI Yogeshwari
possession by Dec 2029 · Prime Group LLP
Jairajratna CHS Ltd
declared completion Jun 2020 · Mumbai Shelter Project Jairajratan LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026