MahaRERA Property Intelligence · Mumbai Suburban
P51800017905 · TILAK NAGAR · promoter Rajesh Malshi Dedhia
| MahaRERA registration | P51800017905 |
| Registered on | 25 Sep 2018 |
| Promoter-declared completion | 30 Dec 2021 |
| Current status | Certificate Signed |
| Against today | about 55 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
Across MahaRERA, Rajesh Malshi Dedhia is the promoter of record on 169 projects, of which 28 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| A AND B WING | 1 | G+16 | 31 Dec 2020 |
25 complaints are on the MahaRERA record for this project, with orders passed in 25. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC006000000057764 | 30/01/2019 | Kishor Bhaskar Borse vs M.s. S.D. Constructions | order passed |
| CC006000000057765 | 31/01/2019 | Chetan Kishor Borse vs M/s S.D. Constructions | order passed |
| CC006000000057854 | 16/03/2019 | Mr.Swapnil B. Shah vs M/s. S,D. Constructions | order passed |
| CC006000000057859 | 16/03/2019 | Dr. Rekha Shimpi vs M/s. S.D. Constructions | order passed |
| CC006000000057860 | 16/03/2019 | Mr. N.M.GHUNDIYAL vs M/s. S.D. Constructions | order passed |
| CC006000000057862 | 16/03/2019 | Mrs. Lata Visharia vs M/s. S.D. Constructions | order passed |
| CC006000000057867 | 16/03/2019 | Mrs Jayshree Ghundiyal vs M/s. S.D. Constructions | order passed |
| CC006000000057868 | 16/03/2019 | Dr.Prashant Shimpi vs M/s. S.D. Constructions | order passed |
| CC006000000057873 | 16/03/2019 | Mrs.Jayaben Dhirajlal shah vs M/s. S.D. Construcions | order passed |
| CC006000000057875 | 16/03/2019 | Arvind Vasudeo Patwardhan vs M/s. S.D. Constructions | order passed |
| CC006000000057878 | 15/03/2019 | Mr. Rajpal Singh vs M/s. S.D. Constructions | order passed |
| CC006000000057882 | 16/03/2019 | Mrs. prachi N. Ghundiyal vs M/s. S.D. Constructions | order passed |
| CC006000000057883 | 16/03/2019 | Mr. Ilesh D. Shah vs M/s. S.D. Constructions | order passed |
| CC006000000057884 | 16/03/2019 | Dr. Manisha Chandan Saney vs M/s. S.D. Constructions | order passed |
| CC006000000057885 | 16/03/2019 | Mrs Revathi Nadar vs M/s. S.D. Constructions | order passed |
| CC006000000057886 | 15/03/2019 | Mr. Chandir Shrichand Talreja vs M/s. S.D. Constructions | order passed |
| CC006000000057887 | 16/03/2019 | Shree Sai Developers and Builders vs M/s. S.D, Constructions | order passed |
| CC006000000057888 | 15/10/2019 | Bharati S Mehta vs M/s. S.D. Constructions | order passed |
| CC006000000057906 | 15/03/2019 | Mr. Namraj J. Sharma vs M/s. S.D. Constructions | order passed |
| CC006000000057908 | 15/03/2019 | Mrs. Draupadi K. Sharma vs M/s. S.D. Constructions | order passed |
| CC006000000057909 | 15/03/2019 | Mr. Keshav J. Sharma vs M/s. S.D. Constructions | order passed |
| CC006000000078706 | 29/03/2019 | Bhupendra Kapasi vs SIA DEVELOPERS | order passed |
| CC006000000058124 | 14/03/2019 | Pankaj Shah vs SIA DEVELOPERS | order passed |
| CC006000000078243 | 14/03/2019 | SANJAY AJANI vs SIA DEVELOPER | order passed |
| CC006000000078244 | 15/03/2019 | Shree Sai Developers and Builders vs SIA DEVELOPERS | order passed |
The promoter has declared 2 court cases on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| Bombay High Court | LODGING NO 414 | 2017 | Pending |
| Maharera | CC006000000057764 | 2019 | Disposed Off |
The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 30 Dec 2021 | 30 Jun 2023 | As per request letter attached , we would request you to grant the extension date for the said project. |
Located at TILAK NAGAR, ROAD CROSSING OF 44 FTS ROAD AND 60 FTS ROAD, Borivali, Mumbai Suburban, 400089. Per the filed land record, the plot is bounded to the north by 44 FTS WIDE ROAD, to the south by 60 FTS WIDE ROAD, to the east by BUILDING NO 81 AND 82 and to the west by CROSSING OF 44 FTS AND 60 FTS. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in JAIHIND CHS LTD?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Rajesh Malshi Dedhia is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026