Mumbai/Project record

MahaRERA · the public record

Jeevan Tara CHS LTD

Vile Parle East, Mumbai · Regent Builders

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2027declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800049161

Delivery and registration

When is the project declared for completion?

Jeevan Tara CHS LTD is registered with MahaRERA as P51800049161 and the promoter has declared completion for 31 Mar 2027.

31 Mar 2027

declared completion

6months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800049161
Registered on01 Feb 2023
Promoter-declared completion31 Mar 2027
Current statusCertificate Signed
Against today6 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Jeevan Tara CHS LTD record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Regent Builders is the promoter of record on 18 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

18projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Jeevan Tara CHS LTD in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
Awing and B Wing1G+11-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Vile Parle East, Mumbai, Azad Road, Andheri, Mumbai Suburban, 400057. Per the filed land record, the plot is bounded to the north by FP No-512 and FP No-513, to the south by FP No-516, to the east by FP No-498 and FP No-499 and to the west by Railway Facility Infrastructure. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport2 km
Bandra Kurla Complex (BKC)4 km
Andheri MIDC / SEEPZ5 km
Powai / Hiranandani business park7 km
Lower Parel / Worli business district11 km
Nariman Point / Fort19 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Regent Builders is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Regent Builders

Regent Builders
FlaggedMumbai Suburban
Regent Builders
FlaggedMumbai Suburban

Other RERA-registered projects in Vile Parle East

Moti Madhav
possession by Sep 2026 · Aadhya Skyvista
Neumec Niwara
possession by Sep 2026 · Neumec Venture
Yeshwant Sadan
possession by Sep 2026 · ARG Life Spaces LLP
Vile Parle Mamata Chsl
possession by Oct 2026 · Dhruv Infrastructure
Vanmala Nivas CHS LTD
possession by Nov 2026 · AMI Infra Realtors
ZEE Nayak
possession by Dec 2026 · Pragatee ZEE

Other RERA-registered projects in Mumbai Suburban

Jhelum
declared completion Dec 2021 · Satre Infrastructure Private Limited
Jigna Residency
declared completion Dec 2024 · Samir Dhirendra Tanna
JMS Business Centre
declared completion Dec 2023 · JMS Realty
Johns Wish
declared completion Dec 2022 · OM Developers
Josville
possession by May 2028 · Meghna Infracon Infrastructure Limited
Joy Legend Wing B
possession by Dec 2026 · Bhavin Jayant Soni

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026