MahaRERA Property Intelligence · Mumbai Suburban

JOHNS WISH

P51800008891 · promoter Om Developers

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP51800008891
Registered on19 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
JOHNS WISH1G+830 Jun 2019

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000005639230/09/2018Arvind Sonawane vs Om Developersorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202230 Jun 2022DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 30/06/2022
30 Dec 202229 Jun 2020Due to non clearance of MCGM policy. Shortage of raw material hence required extension of project.

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 400058. Per the filed land record, the plot is bounded to the north by STONEWALL APARTMENT, to the south by 9 MTR D P ROAD, to the east by STONEWALL APARTMENT and to the west by MARY ALLIEN BUILDING. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Chhatrapati Shivaji Int'l Airport5 km
Bandra Kurla Complex (BKC)8 km
Powai / Hiranandani business park8 km
Lower Parel / Worli business district14 km
Nariman Point / Fort22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

OM Developers is the promoter on 26 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every OM Developers project & its RERA track record →

Other flagged projects by OM Developers

OM Developers
Past its declared completion dateThane

Other RERA-registered projects in Andheri West

Shepherd Horizon
possession by Jul 2026 · Goodbuild India Private Limited
Anutam
possession by Sep 2026 · Truly Highdreams Realtors LLP
Vivan Homes
possession by Dec 2026 · Imprint Estates Pvt Ltd
Alpine Primo
possession by Dec 2026 · Alpine Infraheights LLP
Bella Casa
possession by Dec 2026 · Konark Bella Casa LLP
Hetali Sagar
possession by Dec 2026 · Jayesh Himatlal Pandya

Major developers building in Andheri West

Other RERA-registered projects in Mumbai Suburban

Joseph Villa
declared completion Dec 2024 · K.pateland CO
Josville
possession by May 2028 · Meghna Infracon Infrastructure Limited
Jovial ARK
declared completion Mar 2026 · V R Associates
Joy Alka
declared completion Dec 2018 · Joy Realty Limited
Joy Legend Wing A
declared completion Dec 2019 · Jayant Soni
Joy Legend Wing B
possession by Dec 2026 · Bhavin Jayant Soni

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026