Josville
Bandra-H, Santacruz (W) · MEGHNA INFRACON INFRASTRUCTURE LIMITED
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 02 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 May 2028
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 02 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · PR1180002502565
Delivery and registration
When is the project declared for completion?
Josville is registered with MahaRERA as PR1180002502565 and the promoter has declared completion for 31 May 2028.
31 May 2028
declared completion
20months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 02 Jul 2026
| MahaRERA registration | PR1180002502565 |
| Registered on | 02 Mar 2026 |
| Promoter-declared completion | 31 May 2028 |
| Current status | Certificate Signed |
| Against today | 20 months to the declared date |
Construction
How much construction cost has been reported?
In Josville, ₹74.87 Lakh of a declared ₹1.00 Cr estimated project cost is reported as incurred, about 74.9%, as at the last certified filing with MahaRERA.
74.9%
₹74.87 Lakh
of ₹1.00 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 02 Jul 2026
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for Josville in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 02 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| Josville | 1 | G+11 | - |
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Location, Land & Connectivity
Located at Bandra-H, Santacruz (W), Santacruz, Borivali, Mumbai Suburban, 400054. Per the filed land record, the plot is bounded to the north by Cluster Mumbai Suburban 553, to the south by Existing 9.15M Wide ST. Francis Ave Road, to the east by Arsha Villa and to the west by 2nd Hasnabad Lane. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Bandra Kurla Complex (BKC) | 5 km |
| Lower Parel / Worli business district | 6 km |
| Chhatrapati Shivaji Int'l Airport | 6 km |
| Andheri MIDC / SEEPZ | 10 km |
| Powai / Hiranandani business park | 11 km |
| Nariman Point / Fort | 14 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.