Mumbai/Project record

MahaRERA · the public record

JOANITA VILLA

Andheri West · WESTIN DEVELOPERS PVT. LTD

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900005532

Delivery and registration

When is the project declared for completion?

JOANITA VILLA is registered with MahaRERA as P51900005532 and the promoter has declared completion for 30 Jun 2019.

30 Jun 2019

declared completion

87months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900005532
Registered on11 Aug 2017
Promoter-declared completion30 Jun 2019
Current statusCertificate Signed
Against todayabout 87 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for JOANITA VILLA record 8 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 8 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Westin Developers is the promoter of record on 14 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

14projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for JOANITA VILLA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
JOANITA VILLA1G+15-

Legal and disputes

What disputes are disclosed?

3 complaints are on the MahaRERA record for JOANITA VILLA, with orders passed in 2 of them.

3complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000005597928/08/2018RAYMOND ALIES NUNES vs WESTIN DEVELOPERS PVT LTDorder passed
CC00600000019876021/10/2021Raymond A Nunes vs 1. Shri Vijay Sakharam Prabhu, 2. Shri Amol P. Karpe, 3. Shri Manish J Rach + 5 OTHERS (See page 35)order passed
CC00600000037500230/03/2023WESTIN JOANITA CHS LTD (society) vs WESTIN DEVELOPERS PVT LTDpending / no order on file

A co-operative housing society is recorded as the complainant (WESTIN JOANITA CHS LTD).

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2019Due to delay of commencement certificate of our project.
30 Jun 201930 Jun 2019Road setback issue was not resolved. Airport NOC got delayed. New DP came into effect from January 2019

Location, Land & Connectivity

Located at Andheri West, Mumbai City, Mumbai City, 400058. Per the filed land record, the plot is bounded to the north by CTS NO 436 3 PART, to the south by OM SAI B SRA CO OP CHS, to the east by 40FT WIDE JAI BHAVANI MATA ROAD TO THE EAST and to the west by PLOT BEARING CTS NO 313 478 124. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Chhatrapati Shivaji Int'l Airport5 km
Bandra Kurla Complex (BKC)8 km
Powai / Hiranandani business park8 km
Lower Parel / Worli business district14 km
Nariman Point / Fort22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Westin Developers Pvt. LTD is the promoter on 5 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Westin Developers Pvt. LTD

Westin Developers Pvt. LTD
FlaggedMumbai Suburban
Westin Developers Pvt. LTD
Past its declared completion dateMumbai City
Westin Developers Pvt. LTD
Past its declared completion dateMumbai City

Other RERA-registered projects in Andheri West

Anutam
possession by Sep 2026 · Truly Highdreams Realtors LLP
Vivan Homes
possession by Dec 2026 · Imprint Estates Pvt Ltd
Alpine Primo
Registration suspended · possession by Dec 2026 · Alpine Infraheights LLP
Bella Casa
possession by Dec 2026 · Konark Bella Casa LLP
Hetali Sagar
possession by Dec 2026 · Jayesh Himatlal Pandya
La Alteza
possession by Dec 2026 · Emerald Developers

Major developers building in Andheri West

Other RERA-registered projects in Mumbai City

Jyot Residency
declared completion Jun 2025 · Samcon Builders
K L Victoria
declared completion Feb 2025 · Jeevan Sona Realty AOP
K RAS Residency
possession by Sep 2026 · K RAS Group
Kalaya Tower
declared completion Jun 2026 · Akruti Developers And Builders
Kalpataru Azuro
possession by Dec 2027 · Kalpataru Properties Limited
Kalpataru One - Wing A
possession by Mar 2032 · Kalpataru Properties Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026