MahaRERA Property Intelligence · Mumbai Suburban

JUIPTER

P51800009587 · promoter Marsland Projects

Certificate SignedDue 31 Dec 2018

Delivery & Registration

MahaRERA registrationP51800009587
Registered on22 Aug 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 91 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
JUIPTER1G+13-

Complaints & Orders

5 complaints are on the MahaRERA record for this project, with orders passed in 5. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000002308824/01/2018SUCHITRA AMAL BANERJEE vs MARSLAND PROJECTSorder passed
CC00600000005654612/10/2018SUCHITRA AMAL BENERJEE vs MARSLAND PROJECTSorder passed
CC00600000017157618/11/2019SURESHCHANDRA R BIND vs SHRUTI SANJAY THATTEorder passed
CC00600000023121925/07/2022Surendra Kapoorchand Parmar vs M/s Marsland Projectsorder passed
CC00600000029283427/09/2022Jupiter Allotees Association vs Marsland Projectsorder passed

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400055. Per the filed land record, the plot is bounded to the north by PLOT NO 18 PART, to the south by PANDIT JAWARHARLAL NEHRU ROAD, to the east by PLOT NO 18 PART and to the west by PLOT NO 17. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Andheri MIDC / SEEPZ2 km
Chhatrapati Shivaji Int'l Airport3 km
Powai / Hiranandani business park5 km
Bandra Kurla Complex (BKC)5 km
Lower Parel / Worli business district13 km
Nariman Point / Fort21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Santacruz East

Pruthi Annexe
possession by Sep 2026 · Raja Developers
Crystal Avenue
possession by Nov 2026 · Eternia Realty
Vaibhav Heights
possession by Dec 2026 · RSN Balaji Realtors P LTD
Ambit Vista
possession by Dec 2026 · Ambit Builders & Developers
Atmiya Centria
possession by Dec 2026 · Upturn Properties LLP
Crescent Nexus
possession by Dec 2026 · Ascent Infraspace Private Limited

Major developers building in Santacruz East

Other RERA-registered projects in Mumbai Suburban

Julius Wadi CO- Operative Housing Society
possession by Dec 2026 · Sainath Developers
Justin CO-OP. Hsg. Soc. LTD
possession by Mar 2029 · U. K. Properties
Jvlr 60
possession by Dec 2028 · Rajhem Builders AND Developers LLP
Jvms Clermont
declared completion Dec 2025 · JVM Spaces
Jvms Monica Gardens
possession by Dec 2026 · JVM Spaces
Jvms Shanay Vista
possession by Oct 2028 · M/s. JVM Spaces

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026