MahaRERA Property Intelligence · Mumbai Suburban

KAILASA

P51800017580 · CHEMBUR WEST · promoter Devnani Developers

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP51800017580
Registered on28 Aug 2018
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
KAILASA1G+1331 Dec 2020

Complaints & Orders

2 complaints are on the MahaRERA record for this project, with orders passed in 2. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000007920709/05/2019Ajeet Singh Hinduja and Muskan Kaur Hinduja vs Devnani Developersorder passed
CC00600000039725928/08/2023SUCHETA CHATTERJEE vs SANJAY DEVANANIorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202230 Jun 2022The construction work of our on-going project was halted after the lockdown came into effect due to COVID-19 pandemic, and also lockdown leads to a reverse migration of labourers t

Location, Land & Connectivity

Located at CHEMBUR WEST, SINDHI SOC., Andheri, Mumbai Suburban, 400071. Per the filed land record, the plot is bounded to the north by CTS 244, to the south by CTS 243, to the east by 12 M Wide Road and to the west by CTS 249 ANDCTS 250. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)3 km
Chhatrapati Shivaji Int'l Airport5 km
Powai / Hiranandani business park8 km
Lower Parel / Worli business district9 km
Andheri MIDC / SEEPZ9 km
Nariman Point / Fort16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Chembur

Chembur Deep Jyoti CHS LTD
possession by Jul 2026 · P M Developers
Hubtown Seasons - B Wing
possession by Jul 2026 · Joynest Premises Privatelimited
Gurukripa
possession by Sep 2026 · Inspira Realty And Infra Private Limited
Kranti Heights
possession by Sep 2026 · Sidhivinayak Constructions
Mass Metropolis
possession by Sep 2026 · Grace Urban Development Corporation
Mohite Mrugank
possession by Sep 2026 · Mohite Infraprojects Private Limited

Major developers building in Chembur

Other RERA-registered projects in Mumbai Suburban

Kailash Enclave
declared completion Jun 2024 · Shrreeya Developerss
Kailash Enclave
declared completion Dec 2023 · Keyshine Enterprises
Kailash Heights
declared completion Dec 2019 · Ranjana Construction PVT LTD
Kailash Residency
possession by Aug 2026 · Tridev Shreeji Associates
Kaivalya CO-Ophsg Society LTD
declared completion Jun 2024 · Ankeeta Associates
Kakad Classic
declared completion Jan 2021 · Niraj Kakad Developers LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026