KARTHIK HEIGHTS

KALYAN EAST · GANESH ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

21 Jan 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

21 Jan 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700027587

Delivery and registration

When is the project declared for completion?

KARTHIK HEIGHTS is registered with MahaRERA as P51700027587 and the promoter has declared completion for 21 Jan 2025.

21 Jan 2025

declared completion

20months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700027587
Registered on20 Dec 2020
Promoter-declared completion21 Jan 2025
Current statusCertificate Signed
Against todayabout 20 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KARTHIK HEIGHTS record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KARTHIK HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
KARTHIK HEIGHTS1G+721 Jul 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Kalyan Senior Division Court1352020Pending

Location, Land & Connectivity

Located at KALYAN EAST, KATEMANIVALI, Kalyan, Thane, 421306. Per the filed land record, the plot is bounded to the north by 12 MT DP ROAD, to the south by MATRUKRUPA BUILDING, to the east by RASHIKA APARTMENT and to the west by PRAKASH APARTMENT. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Ganesh Enterprises is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Kalyan East

Kohinoor Eden
possession by Sep 2026 · KGI Realty Private Limited
Kohinoor Eden Ph 2
possession by Sep 2026 · KGI Realty Private Limited
Krishna Glory
possession by Oct 2026 · Tulsi Kimaya Construction
Trimurti Garden
possession by Dec 2026 · SAI Narayan Developers
Rai S Aaragya
possession by Dec 2026 · RAI Residency Private Limited
Rai S Heaven
possession by Dec 2026 · RAI Residency Private Limited

Major developers building in Kalyan East

Other RERA-registered projects in Thane

Kartik Enclave
possession by Dec 2029 · Shivaay Developers
Kartik Ganesh
possession by Dec 2026 · JAI Mata JI Developers
Kartik Homes
possession by Dec 2026 · Kartik Enterprises
Kartik Regency B Wing
possession by Dec 2029 · Hi Tech Realtors
Kashikar Residency
declared completion Mar 2022 · Laukik Buildcon
Kashinath Patkar Nagar
declared completion Dec 2022 · OM Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026