Kartikya Vatika
Cheravali · Sunil Chamanlal Gupta
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Jun 2029
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P52000049066
Delivery and registration
When is the project declared for completion?
Kartikya Vatika is registered with MahaRERA as P52000049066 and the promoter has declared completion for 30 Jun 2029.
30 Jun 2029
declared completion
33months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P52000049066 |
| Registered on | 30 Jan 2023 |
| Promoter-declared completion | 30 Jun 2029 |
| Current status | Certificate Signed |
| Against today | 33 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Kartikya Vatika record 14 quarterly progress reports since registration.
14quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Sunil Chamanlal Gupta is the promoter of record on 5 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
5projects
registered with MahaRERA
0flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Construction
How much construction cost has been reported?
In Kartikya Vatika, ₹6.00 Cr of a declared ₹11.01 Cr estimated project cost is reported as incurred, about 54.5%, as at the last certified filing with MahaRERA.
54.5%
₹6.00 Cr
of ₹11.01 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In Kartikya Vatika, 8 of 161 homes filed with MahaRERA are recorded as sold or booked (6 with registered agreements and 2 booked), about 5%, and 153 remain available.
5%sold
8 of 161 homes
₹1.45 Cr
committed by buyers
Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹91.05 Lakh (about 63%) is recorded as collected and ₹54.20 Lakh as receivable.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
What buyers actually paid: across 8 registered agreements, the effective carpet rate is ₹5,688/sqft, with eight in ten falling between ₹5,193 and ₹6,642 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.
What the filings record, home by home
Read from MahaRERA on 19 September 2026
MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 8 homes carry one, and 153 of the 161 are recorded unsold.
Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:
| Home | Carpet | Filed for the same home on other floors | Based on |
|---|---|---|---|
| 1A-102 | 331 sqft | Rs 5,688 a sq ft typical, over Rs 5,193 to Rs 6,642 | 8 filed at this size |
A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.
In Kartikya Vatika, 124 of the 153 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4 and 161 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| Building No 01 | 1 | G+4 | 56 | - |
| Building No 02 | 1 | G+4 | 52 | - |
| Building No 03 | 1 | G+4 | 53 | - |
Unit mix on the filing: 159 residential and 2 non-residential (shops/offices).
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 30 Jun 2029 | There is a delay in obtaining NOC from Navi mumbai airport authority which impacted construction activity. |
Location, Land & Connectivity
Located at Cheravali, Cheravali Village, Thane, Thane, 410206. Per the filed land record, the plot is bounded to the north by Survey No 57, to the south by Survey No 3 Hissa No 1B, to the east by Survey No 3 Hissa 1B and to the west by Survey No 56. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~33 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Powai / Hiranandani business park | 33 km |
| Bandra Kurla Complex (BKC) | 36 km |
| Chhatrapati Shivaji Int'l Airport | 36 km |
| Andheri MIDC / SEEPZ | 37 km |
| Lower Parel / Worli business district | 39 km |
| Nariman Point / Fort | 41 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.