MahaRERA Property Intelligence · Thane
P51700052542 · KALYAN · promoter Balaji Enterprises
| MahaRERA registration | P51700052542 |
| Registered on | 08 Sep 2023 |
| Promoter-declared completion | 31 Mar 2027 |
| Current status | Certificate Signed |
| Against today | 8 months to the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
MahaRERA's cost filing puts construction at ~66.2% of the estimated project cost incurred as of the last certificate (₹3.68 Cr spent against a ₹5.56 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.
Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.
Of 13 homes filed with MahaRERA, 3 are sold/booked (1 with registered agreements + 2 booked) and 10 remain available (~23% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Buyers have committed ₹58.11 Lakh in agreement value so far. Of that, ₹31.50 Lakh (~54%) is already collected, ₹26.61 Lakh receivable — a read on how far along these sales really are. Note: the project registers 35 homes in total, but this sold/unsold inventory filing covers only 13 of them — the other 22 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.
The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:
| Floor | Unit | Carpet | Reckoner value |
|---|---|---|---|
| Basement | GODOWN | 794 sqft (73.72 sqm) | ₹53.40 Lakh |
| Floor 1 | FLAT 102 | 423 sqft (39.33 sqm) | ₹32.72 Lakh |
| Floor 3 | FLAT 301 | 382 sqft (35.46 sqm) | ₹29.50 Lakh |
| Floor 4 | FLAT 401 | 382 sqft (35.46 sqm) | ₹29.50 Lakh |
| Floor 5 | FLAT 501 | 382 sqft (35.46 sqm) | ₹39.83 Lakh |
| Floor 5 | FLAT 505 | 423 sqft (39.33 sqm) | ₹44.18 Lakh |
| Floor 6 | FLAT 601 | 382 sqft (35.46 sqm) | ₹39.83 Lakh |
| Floor 6 | FLAT 605 | 423 sqft (39.33 sqm) | ₹44.18 Lakh |
| Ground/Floor 0 | SHOP NO.1 | 243 sqft (22.6 sqm) | ₹23.39 Lakh |
| Ground/Floor 0 | SHOP NO.2 | 589 sqft (54.73 sqm) | ₹56.63 Lakh |
⚠ The inventory filing also declares: 22 owner/investor-held. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 35 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| KAUSHALYA HEIGHTS | 1 | G+7 | 35 | - |
Unit mix on the filing: 27 residential and 8 non-residential (shops/offices).
No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.
The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 31 Mar 2025 | 31 Mar 2027 | NON AVAILABILITY OF CONSTRUCTION MATERIAL, LABOUR SHORTAGE, WEATHER CONDITION, FINANCIAL DELAYS |
Located at KALYAN, KALYAN, Kalyan, Thane, 421301. Per the filed land record, the plot is bounded to the north by SAI BABA APARTMENT, to the south by AHILYABAI CHOWK TO GHELADEVJI CHOWK ROAD, to the east by MK GANDHI GUJRATHI PRIMARY SCHOOL and to the west by SHSHIKANT NIWAS. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in KAUSHALYA HEIGHTS?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Balaji Enterprises is the promoter on 9 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:
See every Balaji Enterprises project & its RERA track record →
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026