57units filed as unsoldInventory · 20 September 2026
31 Dec 2028declared completionMahaRERA registration · read 12 Jul 2026
57registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PR1241012500200

Delivery and registration

When is the project declared for completion?

KHATUSHYAM EMPIRE 1 is registered with MahaRERA as PR1241012500200 and the promoter has declared completion for 31 Dec 2028.

31 Dec 2028

declared completion

27months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationPR1241012500200
Registered on03 Jul 2025
Promoter-declared completion31 Dec 2028
Current statusCertificate Signed
Against today27 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KHATUSHYAM EMPIRE 1 record 7 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

How much has actually been sold?

In KHATUSHYAM EMPIRE 1, 0 of 57 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 57 remain available.

0%sold

0 of 57 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KHATUSHYAM EMPIRE 1 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 20 September 2026

What the filings record, home by home

Read from MahaRERA on 20 September 2026

No home in KHATUSHYAM EMPIRE 1 carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 57 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 3,447 a sq ft typical, over Rs 3,447 to Rs 3,556.

A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.

The Reckoner Record lists all 57 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.

See all 57 filed valuations — ₹999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15 and 57 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
WING-B1G+1557-

Unit mix on the filing: 57 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at DIWANMAN, SUNCITY, Vasai, Palghar, 401202. Per the filed land record, the plot is bounded to the north by OTHER GOVERNMENT LAND, to the south by INTERNAL ROAD, to the east by OTHERS LAND and to the west by NALA(WATER NALA). These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~29 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ29 km
Powai / Hiranandani business park31 km
Chhatrapati Shivaji Int'l Airport33 km
Bandra Kurla Complex (BKC)36 km
Lower Parel / Worli business district43 km
Nariman Point / Fort51 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vasai West

Happy Home Jasmine C D
possession by Sep 2026 · Happy Home Corporation
Dream Aura
possession by Dec 2026 · Clement Regency Developers
Vijaya Complex
Not filing quarterly progress reports · possession by Dec 2026 · Padmavati Enterprises
Ashoka Heavens
possession by Dec 2026 · Shree Mahashraman Realtors
Dattani Vertex Building No.4 Wing EF
possession by Dec 2026 · Brijesh Satish Dattani
Gokarna Residency
possession by Dec 2026 · Harshal Anil Acharya

Other RERA-registered projects in Palghar

Khushi Aangan Phase II
declared completion Dec 2022 · Khushi Developers
Kiara
possession by Jun 2029 · Niwas Lifespaces LLP
Kingsmarque Heights
possession by Aug 2027 · Kingsmarque Developers
Kini Pinnacle
possession by Dec 2028 · Kini Lifespace Developers
Kinjal Bliss
possession by Dec 2028 · Kinjal Homes
Kinjal Complex
declared completion Jun 2018 · Kinjal Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.