MahaRERA Property Intelligence · Mumbai City

Kohinoor Square Phase 2

P51900012308 · Dadar West · promoter Kohinoor Ctnl Infrastructure

Certificate SignedDue 30 Dec 2023

Delivery & Registration

MahaRERA registrationP51900012308
Registered on01 Sep 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Kohinoor Ctnl Infrastructure is the promoter of record on 38 projects, of which 5 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+39.

BuildingWingsFloorsDeclared completion
Wing C Comprising of Residential, Energy Centre, Club House, PPL and Captive Parking1G+39-

Complaints & Orders

2 complaints are on the MahaRERA record for this project, with orders passed in 2. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000019779828/07/2021Anish Gupta vs Kohinoor CTNL Infrastructure Pvt Ltd Companyorder passed
CC00600000019779928/07/2021Ridhi Gupta vs KohinoorCTNL Infrastructure Co Pvt Ltdorder passed

Legal & Litigation

The promoter has declared 7 court cases on this project to MahaRERA. 3 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
National Company Law Tribunal Mumbai10272017Resolution Plan Approved
Mumbai Debt Recovery Tribunal No Ii6492017Pending For Filing Consent Terms
National Company Law Appellate Tribunal Delhi1342018Appeal Withdrawn
High Court Mumbai432018Petition Withdrawn
Supreme Court Delhi33732018Pending For Hearing
Supreme Court Delhi12362017Pending For Hearing
National Company Law Appellate Tribunal Delhi1572018Appeal Withdrawn

Location, Land & Connectivity

Located at Dadar West, N.C. Kelkar Road,Shivaji Park,Dadar (west), Ward GNorth, Mumbai City, 400028. Per the filed land record, the plot is bounded to the north by BMC Property, to the south by Fulgoda Apartments, to the east by J K Sawant Marg and to the west by Kohinoor Square Phase 1. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Lower Parel / Worli business district3 km
Bandra Kurla Complex (BKC)5 km
Chhatrapati Shivaji Int'l Airport8 km
Nariman Point / Fort11 km
Andheri MIDC / SEEPZ12 km
Powai / Hiranandani business park12 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Kohinoor Ctnl Infrastructure Company Private Limited is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Kohinoor Ctnl Infrastructure Company Private

Kohinoor Ctnl Infrastructure Company Private Limited
FlaggedMumbai City

Other RERA-registered projects in Dadar West

Arihant Tower
possession by Sep 2026 · Mehta Developers
Palette
possession by Sep 2026 · Suraj Estate Developers LTD
Vijayshree
possession by Sep 2026 · Sugee Eighteen Developers LLP
Yash Trinity
possession by Sep 2026 · Bhalchandra Vinayak Wadnerkar
Sugee Sukrut
possession by Oct 2026 · Sugee Nine Developers LLP
1891 Ekam Parkk
possession by Dec 2026 · Nascent Developers

Major developers building in Dadar West

Other RERA-registered projects in Mumbai City

Krishna Bhuvan C.h.s
declared completion Dec 2019 · Shaunak Dilip Kirkire
Krishna Kunj
possession by Sep 2029 · Endemic Properties LLP
Krishvi Apartments
declared completion Aug 2025 · M/s Shagun Construction
Krishvi Escape
possession by Dec 2026 · Shagun Realty
Krishvi Heights
possession by Aug 2026 · M/s Shagun Associates
Krypton Crown
possession by Mar 2027 · Krypton Creation

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026