MahaRERA Property Intelligence · Thane

KONARK RESIDENCY

P51700008502 · promoter Konark Nirman Pvt

Certificate SignedDue 31 Mar 2019

Delivery & Registration

MahaRERA registrationP51700008502
Registered on19 Aug 2017
Promoter-declared completion31 Mar 2019
Current statusCertificate Signed
Against todayabout 88 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Konark Nirman Pvt is the promoter of record on 54 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
LOTUS1G+2-
LILY1G+2-
ROSE1G+8-
JASMINE1G+8-
MARIGOLD1G+8-
ORCHID1G+8-
DAISY1G+8-
FLORA1G+8-
IRIS1G+8-
CYPRESS1G+8-

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000019472621/11/2020Hare Krishna Realtors vs Konark Nirman Pvt Ltdorder passed

Location, Land & Connectivity

Located at Ulhasnagar, Thane, 421001. Per the filed land record, the plot is bounded to the north by 30 MW DP ROAD, to the south by BHIM NAGAR, to the east by CTS NO 1699 and to the west by CTS NO 1701 P. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~30 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park30 km
Andheri MIDC / SEEPZ33 km
Chhatrapati Shivaji Int'l Airport35 km
Bandra Kurla Complex (BKC)36 km
Lower Parel / Worli business district44 km
Nariman Point / Fort50 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Konark Nirman Pvt. Ltd. is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Konark Nirman Pvt. Ltd.

Konark Nirman Pvt. Ltd.
FlaggedThane

Other RERA-registered projects in Ulhasnagar

Golden City
possession by Dec 2026 · Krishna Infra
Regency Antilia Phase Viii Avana
possession by Dec 2026 · Regency Nirman LTD
Mahan Luxuria
possession by Mar 2027 · Kohinoor Builders & Developers
Kohinoor Gardens
possession by Nov 2027 · KGI Realty Private Limited
Atlanta Avadh
possession by Apr 2028 · Atlanta Globalprojects LLP
Regency Antilia Phase IX Avana
possession by Apr 2028 · Regency Nirman LTD

Major developers building in Ulhasnagar

Other RERA-registered projects in Thane

Konark Solitaire - Phase 1
declared completion Jun 2019 · Konark Realties J.v.
Konark Solitaire - Phase II
declared completion Dec 2022 · Konark Realties J.v.
Kondilkar Residency
declared completion Jan 2019 · Aditi Construction
Kool Breeze Phase II
declared completion May 2018 · Abhishek Shelters LTD
Kores Nakshtra
declared completion Dec 2019 · Kores Limited
Koyna
declared completion Dec 2022 · Shree Shakti Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026